Generator installation proposal, 7 World Trade Center, April 1998 · page 1NYC-WTC_000172137
Contractor submits a $717,890 proposal to install generators and related equipment for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Generator installation proposal, 7 World Trade Center, April 1998 · page 2NYC-WTC_000172137
Contractor submits a $717,890 proposal to install generators and related equipment for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Contract registration memo for 7 World Trade Center lease, May · page 1NYC-WTC_000172141
Memo submitting construction contract registration copies for Mayor's Office of Emergency Management leased space at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #082 memo for blast-resistant door installation, April 1999 · page 1NYC-WTC_000172150
Memo submitting change order #082 to replace existing door and hardware with a blast-resistant door in the radio room.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #087 memo for UPS conversion kit installation, June · page 1NYC-WTC_000172152
Memo submitting change order #087 to install a UPS conversion kit allowing direct power input and output in the office.
Citywide Administrative Services, Dept. of · Box 7DCAS
Architect memorandum regarding fuel oil tank room inspection, March 2000 · page 1NYC-WTC_000172166
Memorandum responding to Port Authority inspector requests for self-closing access hatch and Inergen system tie-ins for the fuel oil tank room.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo re: overhead cabling reorganization at 7 World Trade Center, · page 1NYC-WTC_000172171
A January 14, 2000 memo regarding the reorganization of overhead cabling and reimbursement disputes for work at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #89 for OEM wiring work, Jun 1999 · page 1NYC-WTC_000172195
Submission of change order for power and control wiring installation at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Additional Services Authorization form for OEM audio-visual work, Mar 1999 · page 1NYC-WTC_000172197
Form authorizing revised scope of services for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #019 for projector replacement, Oct 1998 · page 1NYC-WTC_000172199
Contractor submission of change order for replacing projectors at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Credit change order #027, Nov 1998 · page 1NYC-WTC_000172201
Letter from Ambassador Construction submitting credit change order #027 for painting work at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #032 submission, Nov 1998 · page 1NYC-WTC_000172203
Submission of change order #032 for construction work at the Mayor's Office of Emergency Management in 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #4 for cabinetry, Nov 1998 · page 1NYC-WTC_000172208
Proposal from Superior Casework for cabinets and countertops in Room 23-09 at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #36 for generator room waterproofing, Nov 1998 · page 1NYC-WTC_000172211
Submission of change order to waterproof the generator room on the 7th floor using Dex-o-Tex flooring.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #46, 7 World Trade Center, Jan 1999 · page 1NYC-WTC_000172216
Submission of Change Order #46 for $2,168 to provide power supply in room 23-50 at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction fax cover sheet, Dec 23 1998 · page 1NYC-WTC_000172219
Facsimile transmission cover sheet from Ambassador Construction dated December 23, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #56 submission, Jan 1999 · page 1NYC-WTC_000172220
Letter from Ambassador Construction submitting Change Order #56 for electrical outlet installation at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #072 submission, Feb 1999 · page 1NYC-WTC_000172223
Letter from Ambassador Construction submitting Change Order #072 for pantry equipment at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
OEM memo on WTC EOC restoration, Feb 9 1999 · page 1NYC-WTC_000172228
February 9, 1999 memorandum from the Mayor's Office of Emergency Management detailing restoration and equipment orders for 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #85, 7 World Trade Center, May 1999 · page 1NYC-WTC_000172231
Submission of Change Order #85 for $34,401 for additional work related to fuel-oil line routing at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #086 for WTC ductwork, May 1999 · page 1NYC-WTC_000172235
Memo submitting Change Order #086 for rerouting exhaust ducts at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes for 7 World Trade Center, Oct 1998 · page 1NYC-WTC_000172255
Minutes from the fifteenth consultant meeting regarding the Mayor's Office of Emergency Management project at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes for 7 World Trade Center, Oct 1998 · page 2NYC-WTC_000172255
Minutes from the fifteenth consultant meeting regarding the Mayor's Office of Emergency Management project at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes for 7 World Trade Center, Oct 1998 · page 3NYC-WTC_000172255
Minutes from the fifteenth consultant meeting regarding the Mayor's Office of Emergency Management project at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes #16, Nov 10 1998 · page 1NYC-WTC_000172260
Minutes of the sixteenth consultant meeting detailing construction status and fuel oil piping installation.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes #16, Nov 10 1998 · page 2NYC-WTC_000172260
Minutes of the sixteenth consultant meeting detailing construction status and fuel oil piping installation.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes #16, Nov 10 1998 · page 3NYC-WTC_000172260
Minutes of the sixteenth consultant meeting detailing construction status and fuel oil piping installation.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes for 7 World Trade Center, Nov 1998 · page 1NYC-WTC_000172266
Minutes from the eighteenth consultant meeting regarding the Mayor's Office of Emergency Management project at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes for 7 World Trade Center, Nov 1998 · page 2NYC-WTC_000172266
Minutes from the eighteenth consultant meeting regarding the Mayor's Office of Emergency Management project at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Consultant meeting minutes #18, Nov 24 1998 · page 1NYC-WTC_000172268
Minutes of the eighteenth consultant meeting covering project status updates for the Mayor's Office of Emergency Management at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction proposal for OEM cabinets, May 1998 · page 1NYC-WTC_000172278
Proposal from Superior Casework Inc. dated May 27, 1998, for the construction and installation of cabinets at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction proposal for OEM cabinets, May 1998 · page 5NYC-WTC_000172278
Proposal from Superior Casework Inc. dated May 27, 1998, for the construction and installation of cabinets at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction cost estimate for OEM World Trade Center project · page 1NYC-WTC_000172283
Bureau of Space Design document estimating construction costs for the Mayor's Office of Emergency Management program at the World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Revised construction proposal for 7 World Trade Center, June 1998 · page 1NYC-WTC_000172287
Letter enclosing a revised construction proposal and additional bids for the Mayor's Office of Emergency Management at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Scope of work bid for structural steel, May 1998 · page 1NYC-WTC_000172303
Bid document from KS Inc. detailing structural steel framing and metal decking work for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction proposal for 7 WTC renovation, May 1998 · page 1NYC-WTC_000172316
Proposal from Ambassador Construction Company for demolition and construction work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction proposal for 7 WTC renovation, May 1998 · page 2NYC-WTC_000172316
Proposal from Ambassador Construction Company for demolition and construction work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction proposal for 7 WTC renovation, May 1998 · page 3NYC-WTC_000172316
Proposal from Ambassador Construction Company for demolition and construction work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
List of drawings, 7 World Trade Center, May 1998 · page 3NYC-WTC_000172319
Architectural drawing index for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
List of drawings, 7 World Trade Center, May 1998 · page 4NYC-WTC_000172319
Architectural drawing index for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Table of contents, architectural specifications, May 1998 · page 1NYC-WTC_000172323
Index of architectural specification sections for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Table of contents, architectural specifications, May 1998 · page 2NYC-WTC_000172323
Index of architectural specification sections for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Table of contents, architectural specifications, May 1998 · page 3NYC-WTC_000172323
Index of architectural specification sections for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Table of contents, architectural specifications, May 1998 · page 4NYC-WTC_000172323
Index of architectural specification sections for the Mayor's Office of Emergency Management at 7 World Trade Center dated May 4, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction cost estimate addendum for HVAC, May 1998 · page 1NYC-WTC_000172327
Addendum #1 to a construction cost estimate form for HVAC work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
HVAC cost breakdown fax, June 1998 · page 1NYC-WTC_000172328
Fax from KABACK detailing cost adjustments for HVAC controls and dampers at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction Change Order #85, May 1999 · page 1NYC-WTC_000172338
Memo from Ambassador Construction submitting Change Order #85 for fuel oil piping work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
DCAS memo approving construction rent invoice, March 1999 · page 1NYC-WTC_000172351
Memorandum from DCAS approving a construction rent invoice for the Mayor's Office of Emergency Management at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo requesting resubmission of Change Order #81 cost, April 1999 · page 1NYC-WTC_000172360
DCAS official requests review and resubmission of Change Order #81 costs due to insufficient justification for the $8,228.00 amount requested.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo submitting Change Order #87 for UPS conversion kit, June · page 1NYC-WTC_000172368
DCAS official submits Change Order #87 for a UPS conversion kit installation in an office at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS