AMBASSADOR CONSTRUCTION CO.. INC.
April 15, 1999
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #081
Amb.Job # S57-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #081 to perform the following work at
the above referenced premises for the sum of EIGHT THOUSAND TWO HUNDRED
TWENTY EIGHT DOLLARS ($8,228.00):
SCOPE OF WORK
- In radio room on the roof, fasten the existing
three (3) sides of wall paneling to the structural
steel with special clips.
No moving of equipment or electrical work is included.
We trust the above meets with your approval and we look forward to the continued
pleasure of serving you.
Please sign one copy of this letter and return it to our office for our records.
Very truly yours, y / Z
^^A^MdO^ONSTRUCTION co., INC.
Martin Schneider
Vice President
MS:am
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted: Dated:
C \OFFICe\WPWIN\WP00CS'OEI*CaS\0EMCO81 WPO
317 MADISON AVENUE • NEW YORK, NY 10017 -212 922 1020 • FAX 212 949 9762
NYC-WTC_000172360
OCR can misread numbers and units. Confirm readings against the page image before using them.