AMBASSADOR CONSTRUCTION CO,, INC
Mr. Walter Weems
October 16.1998
PageTwo...
7) Per drawing E4-02 dated 9/25/98; y
A. Add one (1) 200amp 3 pole and one (1) 70amp 3 pole breaker in EDPL-23E.
B. Delete one (1) 3 pole 10Oamp breaker in EDPL-23E. —
C. Revise panel ULP-23W and ULP-R from 3 phase 4 witejol phase three wire.
D. Add one (1) 55anip 2 pole breaker in panel ELP-23Ct^^
E. Delete two (2) 1 Samp 1 pole breakers in panel ELP-23C1. J
All panels have been delivered and installed with the branch circuitry and feeders. Panel
EDPL23-E will have to be replaced in its entirety. All branch and feeder wiring will be removed
and then re-installed. Panel LILP23W & R will also have to be replaced. New panels will be
provided and re-installed. New breakers will be installed for panel ELP-23C-1
Electrical Cost . $174400.00
Subtotal Electrical Cost $30,165.00
Additional Cut and Patch .... 2,500.0.0
Subtotal $32,665.00
General Conditions 2,613.00
Overhead and Fee 2.117.00
Insurance ____ 4fi7..DC
Total $37.BB21Kr
In order to perform this work, v/e must an approval for this change order.
Please sign one copy of this return it to our office so we may proceed.
/
If you have any questions, please do not hesitate to contact us.
We trust the above meets with your approval and we look forward to the continued pleasure of
serving you.
Very truly yours,
C^ST^CTm CO.. INC.
.lyiartin Schneider
/ Vice President
cc: Juan Mejia SHC
Glenn Pymento - DCAS
Accepted:____________ Dated: