AMBASSADOR CONSTRUCTION CO, INC.
4
OP’' M
October 15, 1998 **?5^«*«
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #016
Amb. Job #.557-5175
Dear Mr. Weems;
We are pleased to submit herewith our change order #016 to perform the following work at the
above referenced premises for the sum of THIRTY SEVEN THOUSAND EIGHT HUNDRED
SIXTY TWO DOLLARS ($37,862.00):
SCOPE OF WORK
As per electrical plans dated 9/3/98 and 9/25/98 representing revision changes #3 and 4;'
1) On drawing E1-23 dated 9/25/98, relocate panel
ELP-23N3 in the Ian room. Panel and conduits
previously installed.
Electrical Cost $3,300.00
2) On drawing E3-01 dated 9/3/98, tap the secondary
of the 75KVA transformer and feed a new 200amp
switch with shunt trip. This is to redirect the feed
to ATS #7 on the roof.
Electrical Cost $4,310.00
3) Provide service connection to 208 volt single phase
dishwasher per drawing E1-23 dated 9/25/98.
Electrical Cost $1,740.00
4) Add one (1) fire alarm pull station.
Electrical Cost $ 950.00
5) Upgrade wiring to dimming panel from new breaker
in panel EDPL-23E fed by a 70amp breaker.
Electrical Cost $1,825.00
6) Additional switching room 2330, included new and
relocated wiring.
Electrical Cost $ 640.00
Forward. . .