AMBASSADOR CONSTRUCTION CO., INC.
Mr. Walter Weems
October 15, 1998
PageTwo. ..
7) Per drawing E4-02 dated 9/25/98:
A. Add one (1) 200amp 3 pole and one (1) 70amp 3 pole breaker in EDPL-23E.
B. Delete one (1) 3 pole WOamp breaker in EDPL-23E
C. Revise panel ULP-23W and ULP-R from 3 phase 4 wire to 1 phase three wire.
D. Add one (1) 50amp 2 pole breaker in panel ELP-23C1.
E. Delete two (2) 15amp 1 pole breakers in panel ELP-23C1.
All panels have been delivered and installed with the branch circuitry and feeders. Panel
EDPL23-E will have to be replaced in its entirety. All branch and feeder wiring will be removed
and then re-installed. Panel ULP23W & R will also have to be replaced. New panels will be
provided and re-installed. New breakers will be installed for panel ELP-23C-1.
$17,400,00
Subtotal Electrical Cost $30,165.00
Additional Cut and Patch 2,500.00
Subtotal $32,665.00
General Conditions 2,613.00
Overhead and Fee 2,117.00
Insurance 467,00
Total $37,862.00
In order to perform this work, we must have an approval for this change order.
Please sign one copy of this letter and return it to our office so we may proceed.
If you have any questions, please do not hesitate to contact us.
We trust the above meets with your approval and we look forward to the continued pleasure of
serving you.
Very truly yours,
^^Mj^^^^^R^^lMST^CTI^CO., INC.
Martin Schneider
Vice President
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted:_______________ Dated: