NOJ 23 '98 15.00 FR AnOASSflDOR CONSTR. C0212 949 9762 TO 7325190
P.01/03
AMBASSADOR CONSTRUCTION CO., INC
■^\
.71 \
November 13,1998
6»/
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York. NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #016R
Amb, Job#S57-5175
Dear Mr. Weems;
We are pleased to submit herewith our change order #016R to perform the following work at
the above referenced premises for the sum of TWENTY ONE THOUSAND FIVE HUNDRED
NINETEEN DOLLARS ($21,519.00);
SCOPE OF WORK
As per electrical plans dated 9/3/98 and 9/25/98 representing revision changes #3
and 4;
1) On drawing El-23 dated 9/25/98. relocate panel
ELP-23N3 in the Ian room Panel and conduits
previously installed.
Electrical Cost $3,300.00
2) On drawing E3-01 dated 9/3/98, tap the secondary
of the 75KVA transformer and feed a new 200amp
switch with shunt trip. This is to redirect the feed
to ATS #7 on the roof.
Electrical Cost $4,810.00
3) Provide service connection to 208 volt single phase
dishwasher per drawing El-23 dated 9/25/98.
Electrical Cost $1,740.00
4) Add one (1) fire alarm pull station.
Electrical Cost $ 950.00
5) Upgrade wiring to dimming pane! from new breaker
in panel EDPL-23E fed by a 70amp breaker.
Electrical Cost $1,825 00
Forward.. .