AMBASSADOR CONSTRUCTION CO., INC.
♦
January 18.1999
Mr. Walter Weems
Silverstein Properties, Inc,
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 and 23rd Floors
Change Order #055
Amb. JobJLSS7-51T5
Dear Mr. Weems'
We are pleased to submit herewith our change order #055 for the following work at the above
referenced premises for the sum of THIRTY FOUR THOUSAND NINE HUNDRED FIFTY
FOUR DOLLARS ($34,954.00):
SCOPE OF WORK
In the loading dock and lobby areas where the fuel oil lines were to be installed below the
concrete slab, the electncian had to fix alt the conduits damaged by the chopt^ng of the
concrete. These conduits were never indicated on the drawings to be in that location.
In order to fix these conduits, they had to be traced out for all the circuiting. New conduits and
wire had to be installed.
Additional chopping was performed to expose the existing steel beams and plates that were
interpreting with the new fuel oil lines so the engineer could examine them.
The following are the costs for the above work.
Electrical work - RB Samuels' Work Order #27823 $19,170.00
Concrete Chopping .10,986.00
Subtotal $30,156.00
General Conditions 2,412.00
Overhead & Fee 1,954.00
Insurance 432.00
Total $34,954.00
Forward...