← Document results/7DCAS/Mayor's Office of Emergency Management 7 World Trade Center Change Order #044 Amb. Job #S57-5175
Document / 2 pages

Change Order #44 for fuel piping, 7 WTC, Dec 1998

Machine-extracted title · confidence 95%

Ambassador Construction submits Change Order #44 to install fuel oil piping and enclosures at 7 World Trade Center.

NYC-WTC_000168566–000168567

Folder label: “Mayor's Office of Emergency Management 7 World Trade Center Change Order #044 Amb. Job #S57-5175

Page image
Scanned page image, NYC-WTC_000168566
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

DEC 23 ’98 12=38 FR hMBASShDOR CONSTR. C0212 949 9762 TO 7325190 P.05/07

AMBASSADOR CONSTRUCTION CO., INC.

December 23, 1998

Mr. Walter Weems Silverstein Properties Inc. 7 World Trade Center New York. NY 10048

Re; Mayor’s Office of Emergency Management 7 World Trade Center Change Order #044 Amb. Job#S57r5J75

Dear Mr. Weems;

We are pleased to submit herewith our change order #044 to perform the following work at the above referenced premises for the sum of ($.00).

SCOPEOFWORK Furnish and install the fuel oil piping in accordance with Swanke Hayden Connell sketch dated 12/14/98 revise routing. The following are the costs; - Furnish and install 2 hour rated enclosure of lath with two (2) inches of plaster around pipes suspended box. $15,470.00 - Remove and replace sheetrock ceilings $2,500.00 - Paint ceiling $1,500.00 - Patch block .J1.5.00.0.Q Subtotal $20,970.00 General Conditions 1,678.00 Overhead and Fee 1,359.00 Insurance ___ _30.0.QQ Total $24,307.00

We trust the above meets with your approval and we look forward to the continued pleasure of serving you.

Continued,..

317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020. FAX 212 949 9762

NYC-WTC_000168566

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168566Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #067 submission, 7 WTC, Feb 1999 · Box 7DCAS

NYC-WTC_000171464

Ambassador Construction letter dated February 10, 1999, submitting Change Order #067 for $2,694 to assemble cords, relocate speaker strobes, and provide circuits.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.977

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171766 · Box 7DCAS

Cover letter submitting Change Order #44 for $24,307 to install fuel oil piping at 7 World Trade Center.

Filed in the same folder

NYC-WTC_000168573 · Box 7DCAS

Ambassador Construction submits Change Order #41 to install revised antenna support details at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168552 · Box 7DCAS

Memo submitting Change Order #49 to provide ceiling tiles and relocate sprinkler heads in the press room.

Similar indexed content

NYC-WTC_000171882 · Box 7DCAS

Ambassador Construction submits Change Order #47 for stainless steel generator flexes to address height restrictions at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168576 · Box 7DCAS

Ambassador Construction submits Change Order #40 to weld new rebar and chop concrete at 7 World Trade Center.

Similar indexed content

Compare copies and versions →