DEC 21 ’98 14=20 FR AMBASSADOR CONSTR. C0212 949 9762 TO 7325190 P.02/06
AMBASSADOR CONSTRUCTION CO . INC
December 21,1998
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re: Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #040
AmKJjohJS57r517.5
Dear Mr. Weems:
We are pleased to submit herewith our change order #040 to perform the following
work at the above referenced premises for the sum of TWENTY SIX THOUSAND
FOUR HUNDRED TWENTY SEVEN DOLLARS ($26,427.00).
SCOPE OF WORK
As per the engineer’s verbal instructions to weld
new rebar to existing rebar intrench with 3" over lap
at each end. In order to expose the end if the existing
rebar, the concrete has to be chopped away.
New rebar and welding $7,800.00
Chop existing concrete $15,000.00
Subtotal $22,800.00
General Conditions 1,824.00
Overhead and Fee 1,477.00
Insurance ..... 325.0.0
Total $26,427.00
Aitacnate
If welding of rebar has to be performed on Overtime Add $4,080.00
We trust the above meets with your approval and we look forward to the continued
pleasure of serving you.