AMBASSADOR CONSTRUCTION CO. INC.
♦ December 21,1998
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re: Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #040
Amb.Job#S57^517.5
Dear Mr. Weems:
We are pleased to submit herewith our change order #040 to perform the following
work at the above referenced premises for the sum of TWENTY SIX THOUSAND
FOUR HUNDRED TWENTY SEVEN DOLLARS ($26,427.00).
SCOPE_OKWORK
As per the engineer’s verbal instructions to weld
new rebar to existing rebar intrench with 3" over lap
at each end. In order to expose the end Of the existing
rebar, the concrete has to be chopped away.
New rebar and welding $7,800.00
Chop existing concrete __$-15,000.00
,0 Subtotal $22,800.00 '
General Conditions 1,824.00
Overhead and Fee 1,477.00
' ff ■; Insurance 326.00
Total
Alternate
If welding of rebar has to be performed on Overtime Add $4,080.00
We trust the above meets with your approval and we look forward to the continued
pleasure of serving you.