← Document results/7DCAS/Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #082 Arnb. Job # S57-5175
Document / 2 pages

Change Order #82 submission, 7 WTC, April 1999

Machine-extracted title · confidence 95%

Contractor submits Change Order #82 for $8,313 to replace the radio room door with a new blast-resistant door.

NYC-WTC_000168431–000168432

Folder label: “Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #082 Arnb. Job # S57-5175

Page image
Scanned page image, NYC-WTC_000168431
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

=i AMBASSADOR CONSTRUCTION CO., INC.

n APR 2 2 1999

April 21, 1999

Mr. Walter Weems Silverstein Properties, Inc. 7 World Trade Center New York, NY 10048

RE; Mayor’s Office of Emergency Management 7 World Trade Center -1, 7 & 23rd Floors Change Order #082 Amb. Job #557-5175

Dear Mr. Weems;

We are pleased to submit herewith our change order #082 to perform the following work at the above referenced premises for the sum of EIGHT THOUSAND THREE HUNDRED THIRTEEN DOLLARS ($8,313.00):

SCOPE OF WORK To replace the existing hollow metal frame, door and hardware on the radio room and furnish and install a new blast resistance door with category 4-hurricane force. Also included will be the steel plates required.

Breakdown Blastproof doors, frame hardware $3,837.00 Steel plates $1,000.00 Removal and installation $1,750.00 Painting $500.0(3 Subtotal $7,087.00 General Conditions 567.00 Overhead & fee 536.00 Insurance 123.00 Total $8,313.00

Continued. . .

317 MADISON AVENUE • NEW YORK, NY 10017 - 212 922 1020 • FAX 212 949 9762

NYC-WTC_000168431

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168431Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change order #108 cover letter, Dec 17 1999 · Box 7DCAS

NYC-WTC_000171573

Ambassador Construction cover letter dated December 17, 1999 submitting change order #108 for video cable connections at the Mayor's Office of Emergency Management.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.979

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000173903 · Box 7DCAS

Ambassador Construction submits Change Order #082 for $8,313 to replace a hollow metal door with a blast-resistant one at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168612 · Box 7DCAS

Ambassador Construction submits Change Order #025 for structural support work on the roof of 7 World Trade Center.

Similar indexed content

NYC-WTC_000173879 · Box 7DCAS

A memo submits Change Order #25 for $36,199 to install steel supports and beams for microwave dishes on the roof of 7 World Trade Center.

Similar indexed content

NYC-WTC_000168601 · Box 7DCAS

Submission of Credit Change Order #27 for painting the LAN room floor instead of installing VCT flooring at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171855 · Box 7DCAS

Letter detailing Change Order #41 for revised antenna support details installed into beam webs at the Office of Emergency Management.

Similar indexed content

Compare copies and versions →