AMBASSADOR CONSTRUCTION CO, INC.
November 13, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor's Office of Emergency Management
7 World Trade Center -1,7 & 23rd Floors
Change Order #025
Amb.Job #557-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #025 to perform the following work at
the above referenced premises for the sum of THIRTY SIX THOUSAND ONE HUNDRED
NINETY NINE DOLLARS ($36,199.00);
SCOPE OF WORK
As per architect’s sketches FSK-26, FSK-27 and engineer’s sketch SK-S-RA for the
structural support for microwave dishes at bulk head wall in the roof. The following is a
breakdown of the additional costs;
- Steel 3 tube supports and two (2) new
12x19 beams and grating. $22,660.00
- Fireproofing and patch block work. 5,040.00
- Cut three (3) holes in metal siding. 1,540.00
- New 2" conduit for antenna. 1.990.00
Subtotal $31,230.00
General Conditions 2,498.00
Overhead and Fee 2,024.00
Insurance ___ 447.00
Total $36,199.00
Please notify us if we are to proceed with this work.
Continued. . .