AMBASSADOR CONSTRUCTION CO., INC.
January 18, 1999
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York. NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Change Order #053
Amb.4oJ3JtS.57-5178
Dear Mr. Weems:
We are pleased to submit herewith our change order #053 to perform the following additional
work at the above referenced premises for the sum of THOUSAND HUNDRED DOLLARS
($2,898.00):
SCOPE OF WORK
As per R.B Samuels work orders #28491 and #26530 the following work was performed as
additional work:
#28491 - Electricians were requested to mount
computer equipment in the Ian room and patch
cables.
Cost 16 hours X 95.80 $1,533.00 /DQ-D
General Conditions 123.00
Overhead & Fee 99.00
Insurance __ 22.00
Order Total $1,777.00
#26350 - Furnish and install and install Kendoff
supports to the bottom of the A.V. racks in Ian
room. Racks would not fit over electrical floor
boxes. This work was not shown on the
drawings.
Cost Labor 7 x 95.80 $671.00
Material „.296J)0
< L-
Job Total $967.00
General Conditions 77.00
Overhead & Fee 63.00
Insurance __ 14.00
Total $1,121.00
Forward. . .