NAR 23 ’99 16:47 FR AMBASSADOR CONSTR. C0212 949 9762 TO 7325190 P.02/03
AMBASSADOR CONSTRUCTION CO., INC
March 23. 1999
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re: Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #044R
Amb^JofcL#S57-5175
Dear Mr. Weems.
We are pleased to submit herewith our revised change order #044R to perform the
following work at the above referenced premises for the sum of EIGHTY FIVE
THOUSAND EIGHT HUNDRED NINETY THREE DOLLARS ($85,893-00):
SC.QPE.QF WORK
As per Swanke Hayden Connell’s revised sketch SK-58, FSK-50 dated 3/19/99 for
the work on the fuel oil lines their supports and enclosure all sides.
Support, columns enclosures $36,270.00
Concrete encasement around pipe 15.650.00
New route for fuel oil lines 12,500.00
Miscellaneous patching sheetrock & block 5,500.00
Painting 2,600.00
Electrical hook-up for welding _ 1,500.00
Subtotal $73.920 00
General Conditions 5,914.00
Overhead & Fee 4,790.00
insurance 1,2600
Total $85,893.00
Attemate:
If steel work has to be performed on overtime add $9,458.00
We have not included in this cost any other work on overtime or standby time for
this work except for the alternate.
Continued. . .
317 MADISON AVENUE • NEW YORK. NY 10017 • 212 922 1020 • FAX 212 949 9762
NYC-WTC_000168439