AMBASSADOR CONSTRUCTION CO., INC.
November 13, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York. NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #016R
ATOb.JfibJSLS5Z=517J5
Dear Mr. Weems:
We are pleased to submit herewith our change order #016R to perform the following work at
the above referenced premises for the sum of TWENTY ONE THOUSAND FIVE HUNDRED
NINETEEN DOLLARS ($21,519.00);
SCOPE OF WORK
As per electrical plans dated 9/3/98 and 9/25/98 representing revision changes #3
and 4;
1) On drawing El-23 dated 9/25/98, relocate panel
ELP-23N3 in the Ian room. Panel and conduits
previously installed.
Electrical Cost $3,300.00
2) On drawing E3-01 dated 9/3/98, tap the secondary
of the 75KVA transformer and feed a new 200amp
switch with shunt trip. This is to redirect the feed
to ATS #7 on the roof.
Electrical Cost $4,310.00
3) Provide service connection to 208 volt single phase
dishwasher per drawing E1-23 dated 9/25/98.
Electrical Cost $1,740.00 / 6 b'
4) Add one (1) fire alarm pull station.
Electrical Cost $ 950.00
5) Upgrade wiring to dimming panel from new breaker
in panel EDPL-23E fed by a 70amp breaker.
Electrical Cost $1,825.00
Forward...
317MADISON AVENUE, NEW YORK. NY 10017,212922 1020, FAX2129499762
98X P,02
NOU-17-1998 15=57 212 949 9762
NYC-WTC_000171897
OCR can misread numbers and units. Confirm readings against the page image before using them.