NYC Law Department release
Independent mirror · updated as the City releases more · v1.2.6
← Document results/7DCAS/Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #016R Amb. Job #S57-5175
Document / 3 pages

Change Order #016R submission, Ambassador Construction, Nov 1998

Machine-extracted title · confidence 95%

Ambassador Construction submits Change Order #016R for electrical work at the Mayor's Office of Emergency Management on November 13, 1998.

NYC-WTC_000171897–000171899

Folder label: “Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #016R Amb. Job #S57-5175

Page image
Scanned page image, NYC-WTC_000171898
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

NOU jjS:02 FR flMBASSflDOR CONSJR. C0212 949 9762 TO 6694107 P.03/36

AMBASSADOR CONSTRUCTION CO., INC

Mr.Walter Weems November 13, 1998

Page Two...

6) Additional switching room 2330, included new and relocated wiring. Electrical Cost $ 640.00

7) Per drawing E4-02 dated 9/25/98; (DELETED) A. Add one (1) 200amp 3 pole and one (1) 70amp 3 pole breaker in EDPL-23E. B. Delete one (1) 3 pole lOOamp breaker in EDPL-23E. C. Revise panel ULP-23W and ULP-R from 3 phase 4 wire to 1 phase three wire. D. Add one (1) 50amp 2 pole breaker in panel ELP-23C1. E. Delete two (2) 15amp 1 pole breakers in panel ELP-23C1.

All panels have been delivered and installed with the branch circuitry and feeders. Panel EDPL23-E will have to be replaced in its entirety. All branch and feeder wiring will be removed and then re-installed. Panel ULP23W & R will also have to be replaced. New panels will be provided and re-installed. New breakers will be installed for panel ELP-23C-1.

This above work has been changed by Cosentini’s sketches FSK-2, 3, 4, 7 and 9 as per the following wiring changes and fusing changes:

- Re-route eight (8) 1-pole circuits from ELP 23C to ELP 23C1 and add one (1) 3-pole 100A CB to ELP 23C - EDPL-23E - Add one (1) 3-poIe 70A CB - ELP - 23W- Delete three (3) one pole 15 A CB’s and one (1) 3-pole 70 A CB - Change wiring for UPS’s from 2#1, 2 #2 and 1 #250 MCM to 3 #4, 1 #2/0 and 2 #4. - ELP R - Delete three (3) 1-pole 15 A CB’s - ELP R - Add one (1) 3-pole 50A and one (1) 3-pole 70A - Downsize fusing in feeder disconnect from 150A to 70A. -As per FSK-8 add one (1) speaker/strobe Electrical Cost __ $3.^.QQJD.O Subtotal Electrical Cost $17,065.00 Additional Cut and Patch __ XSaO-OD Subtotal $18,565.00 General Conditions ’b 1,485.00 Overhead and Fee 1,203.00 Insurance । / ____ 2_6.OG Total 21,519.00

Forward...

NOU-17-1998 15=58 212 949 9762 98X P.03 NYC-WTC_000171898

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171898Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Revised Change Order #024R submission, Nov 1998 · Box 7DCAS

NYC-WTC_000171914

Ambassador Construction submits revised Change Order #024R for switch installation at the Mayor's Office of Emergency Management on November 5, 1998.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.962

machine-extracted · confidence unavailable · Check page ↗
Credit change order #027, Nov 1998 · Box 7DCAS

NYC-WTC_000172201

Letter from Ambassador Construction submitting credit change order #027 for painting work at 7 World Trade Center.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.950

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000168642 · Box 7DCAS

Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.

Similar indexed content

NYC-WTC_000173884 · Box 7DCAS

Ambassador Construction submits Change Order #016R for $21,519 to relocate a panel and tap a transformer at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171903 · Box 7DCAS

Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.

Similar indexed content

NYC-WTC_000168647 · Box 7DCAS

Change Order #16 submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated October 15, 1998.

Similar indexed content

NYC-WTC_000171914 · Box 7DCAS

Ambassador Construction submits revised Change Order #024R for switch installation at the Mayor's Office of Emergency Management on November 5, 1998.

Similar indexed content

Compare copies and versions →