Part I: Work Plan — Decontamination/Deconstruction
133-135 Greenwich Street and 21-23 Thames Street
Airtek Project 05-0701— Rev 2 August 10, 2005
representative waste will be collected by the Environmental Consultant for
analysis by Full TCLP and RCRA characteristics. Based on the results of TCLP
testing, the waste will be characterized according to any RCRA exceedances.
Disposal will be only to facilities licensed to accept the waste so characterized.
Transportation and Disposal will be as noted above.
8.5 Site Work:
Contractor will perform proper dust control during any demolition or removal
work. The procedures too be followed with regards to visible emissions are
specified in the ECAMP.
The Contractor will comply with all federal and local laws regarding noise
control.
All work will be done by appropriately qualified labor. The Contractor will be
responsible for employing qualified tradesmen for the duration of Contractor's
contract work on this project.
All work is to be performed in accordance with the latest standards as established
by OSHA.
Demolition of a 2-story brick structure, and 5-story brick structure:
a. All existing interior garbage, furniture, fixtures, equipment and surfacing
materials (plaster/wallboard/ceiling systems, etc.) will have been removed
under Phase III above.
b. Remove and dispose of existing brick party wall attached to the South side of
120 Cedar Street Work includes patching holes after demolition. Work dots
not include waterproofing.
c. Complete demolition of above grade structures and ground level framing.
Existing foundation wall, vaults and sidewalk will remain.
d. Remaining exposed cellar slab will be left free from demolition debris.
e. All utilities serving the buildings will be disconnected as required before any
removal and/or demolition is started.
f. Removal and dispose of roof, flashing and associated roofmg material.
g. Obtain and secure all required permits to complete demolition work, including
but not limited to demolition permit, fence permit, sidewalk closing permit,
etc. Cost for obtaining permits is the responsibility of this trade contractor.
h. Upon completion of demolition work, demolition contractor will provide a
"berm" along the foundation walls around the perimeter of the site. The berm
will be used to temporarily support the foundation walls until the excavation /
foundation contractor starts work. The berm will be set on a 45 degree angle
and start from the top of existing foundation wall to the cellar slab,
NYC-WTC 000134897