Part I: Work Plan — Decontamination/Deconstruction
133-135 Greenwich Street and 21-23 Thames Street
Airtek Project 05-0701 — Rev 4 September 29, 2005
Contractor will provide and maintain a plywood fence along Greenwich and
Thames Streets with gates along the front and side of the property. All work to be
coordinated with NYC DOB temporary fence permit. Upon completion of the
Contractor's work, the fence and gates will be left in an acceptable condition, with
gates in locations approved by, and coordinated with, the General Contractor.
General Contractor will obtain fence permit(s) and maintain permit(s) for the
duration of the project. Fence will comply with NYC Department of Building
requirements and will be constructed of minimum 5/8" exterior grade plywood on
two by four frames. Fence will be painted Dark Blue and will have "Post No
Bills" painted a maximum of 10 feet on center. Fence will be constructed with
wood or metal posts at regular intervals. Post will be sunk into the ground as
required to make them free standing without bracing or outriggers. Fence will be
constructed such that sections of it are easily removable without disturbing
remaining sections. Blind spots will not be created on sidewalk.
8.4 Waste Management — Conventional Demolition:
Conventional demolition will involve only the remaining wood structure and
masonry exterior of the buildings. As detailed in the WMP (submittal Part N),
representative waste will be collected by the Environmental Consultant for
analysis by Full TCLP and RCRA characteristics. Based on the results of TCLP
testing, the waste will be characterized according to any RCRA exceedances.
Disposal will be only to facilities licensed to accept the waste so characterized.
Transportation and Disposal will be as described in Part N of the Submittal,
"Waste Management Plan" Sections 9, 10 & 11. Records of hazardous waste
determinations and hazardous waste manifests will be retained for a period of at
least three years from the completion of the project.
8.5 Site Work:
Contractor will perform proper dust control during any demolition or removal
work. The procedures to be followed with regards to visible emissions are
specified in the ECAMP.
The Contractor will comply with all federal and local laws regarding noise
control.
All work will be done by appropriately qualified labor. The Contractor will be
responsible for employing qualified tradesmen for the duration of Contractor's
contract work on this project.
All work is to be performed in accordance with the latest standards as. established
by OSHA.