List of architectural drawings for Bulletin #1, July 1998 · page 4NYC-WTC_000167669
Index sheet listing architectural drawings including floor plans and ceiling layouts issued for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Fax memo: Painting metal panels, Nov 1998 · page 1NYC-WTC_000167863
Transmittal regarding painting procedures for metal panels in the field of construction at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Fax memo: Drainage and slab replacement drawings, Dec 1998 · page 1NYC-WTC_000167873
Transmittal of additional drain requirements and revised drawings for slab replacement at the loading dock.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo: Transformer and panel installation locations, Nov 1998 · page 1NYC-WTC_000167880
Transmittal of revised drawings specifying transformer installation in room 23-05 and panel locations for OEM.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo: FSK clarifications and louver shop drawings, Nov 1998 · page 1NYC-WTC_000167881
Transmittal of clarification documents and louver shop drawings for construction use at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo: Revised and new FSKs, Nov 1998 · page 1NYC-WTC_000167886
Transmittal of revised and new FSK drawings for the Mayor's Office of Emergency Management project.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo requesting construction variations for Mayor's suite, Oct 1998 · page 3NYC-WTC_000167896
Official request from OEM Director for specific construction changes to the Commissioner's Suite.
Citywide Administrative Services, Dept. of · Box 7DCAS
Fax clarifying floor box locations for telecom, Oct 1998 · page 1NYC-WTC_000167899
Transmission of FSK clarifications regarding raised floor box locations and coordination requirements.
Citywide Administrative Services, Dept. of · Box 7DCAS
Distribution list, 7 World Trade Center 23rd floor SHCA drawing, · page 2NYC-WTC_000168221
Distribution list for SHCA architectural drawing set for Mayor's Office of Emergency Management space at 7 World Trade Center dated November 21, 1997.
Citywide Administrative Services, Dept. of · Box 7DCAS
Work order for lighting installation, 7 WTC, Feb 1999 · page 1NYC-WTC_000168429
Memo detailing costs for installing recess light fixtures in the EEOC area due to ceiling height conflicts.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #3 and #4 summary memo, 7 WTC, Sept · page 1NYC-WTC_000168678
Memo summarizing costs for revised Change Orders #3 and #4 regarding A/V work at the Mayor's Office of Emergency Management in 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
SM&W proposal #99-669 for OEM audiovisual systems, Oct 20 1999 · page 1NYC-WTC_000171350
Proposal from SM&W regarding the configuration of audiovisual and communication systems for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Invoice for change order #3, 7 WTC, Jan 1999 · page 1NYC-WTC_000171436
Benjamin Maintenance invoice dated January 26, 1999, for $9,679 regarding change order #3 at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Roofing details for new curb patching, 7 World Trade Center, · page 1NYC-WTC_000171437
Transmittal of roofing patching details and instructions for pouring a new concrete curb over an existing membrane.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order request #1 for OEM work, Jan 1999 · page 1NYC-WTC_000171459
Letter from Computer Floors Inc. dated January 28, 1999, requesting a change order for $4,750 regarding work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order directive for OEM Inergen supply, July 1998 · page 1NYC-WTC_000171489
Contractor directive to install connected reserve Inergen supply including cylinders and valves as part of Change Order number 32.
Citywide Administrative Services, Dept. of · Box 7DCAS
Request for proposal on fire-rated hatch replacement at 7 WTC · page 1NYC-WTC_000171497
Request for a proposal to replace an existing fire-rated hatch with a self-closing unit activated by the Inergen system at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #113 for 7 WTC hatch work, June 2000 · page 1NYC-WTC_000171501
Formal change order document for $3,253 to replace a fire-rated hatch at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Hardware quotation for 7 WTC partition work, Jan 2000 · page 1NYC-WTC_000171512
Quotation from Builders Contract Hardware to supply door gasketing and hardware for a partition at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Quotation for astragal materials and installation, January 2000 · page 1NYC-WTC_000171558
Material and labor quotation from architectural hardware supplier for astragal installation at 7 World Trade Center 23rd floor.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order for electrical riser installation, 7 World Trade Center, · page 1NYC-WTC_000171626
Proposal to install galvanized conduit and fiber optic cables between the loading dock and 23rd floor LAN room for $45,000.
Citywide Administrative Services, Dept. of · Box 7DCAS
Purchase order or invoice for TV carts, Mar 1999 · page 1NYC-WTC_000171650
Document detailing the purchase of two Luxor TVP 44 TV carts for the Mayor's Office of Emergency Management at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #778-01 for overtime labor, 7 WTC, Dec 1998 · page 1NYC-WTC_000171668
Change order #778-01 from Miller-Druck for overtime field labor at 7 World Trade Center dated December 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order for recessed lighting, 7 WTC, Feb 1999 · page 1NYC-WTC_000171675
Letter from Kaback regarding change order for installing recessed lighting boxes at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Credit memo for NEC monitors, Apr 1999 · page 1NYC-WTC_000171680
Invoice credit for eight NEC XP29 monitors and installation labor dated April 26, 1999.
Citywide Administrative Services, Dept. of · Box 7DCAS
Scaffold and shed proposal, 7 WTC lobby, June 1999 · page 1NYC-WTC_000171748
Proposal from York Scaffold Equipment Corporation to furnish interior scaffolding in the 7 World Trade Center lobby.
Citywide Administrative Services, Dept. of · Box 7DCAS
Superior Caseworks proposal for OEM project, Nov 1998 · page 1NYC-WTC_000171819
Letter from Superior Caseworks Inc. proposing construction delivery and installation of cabinets for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #26 submission, 7 WTC, Nov 1998 · page 3NYC-WTC_000171821
Letter from Ambassador Construction submitting change order #26 for drywall and electrical patching work at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change Order #2 proposal for cabinets and countertops, Nov 1998 · page 1NYC-WTC_000171829
Proposal for change order #2 to install cabinets, countertops, and paneling at the Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Waterproofing specification for concrete curbs, Sept 1998 · page 5NYC-WTC_000171835
Letter specifying protective measures for existing Kemperol membrane before pouring new concrete curbs at the Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Letter detailing lighting module requirements, Jan 1999 · page 1NYC-WTC_000171868
January 1999 letter detailing the need for two Crestron CNRY-8 modules to resolve Lutron lighting interface incompatibilities.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo summarizing Change Order #51 cost changes, Jan 1999 · page 3NYC-WTC_000171872
Internal memo summarizing net cost changes for shelving height modifications and unit additions at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Quote for generator exhaust flexes, Dec 1998 · page 1NYC-WTC_000171884
H.O. [name] Company submits a quote for three stainless steel exhaust flexes required for generators at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Electrical work quotation, 7 WTC, October 1998 · page 1NYC-WTC_000171900
Quotation for electrical modifications including panel relocation, transformer work, dishwasher connection, and fire alarm.
Citywide Administrative Services, Dept. of · Box 7DCAS
Response regarding OEM CO #016 panel approval status, Oct 1998 · page 1NYC-WTC_000171909
Contractor correspondence stating that electrical panels were approved without notation but work remains unexecuted as of October 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Visual proposal for OEM EOC control update, Nov 1998 · page 1NYC-WTC_000171918
Proposal document from Visual regarding an EOC control update project for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Letter regarding penthouse siding modification, Nov 1998 · page 1NYC-WTC_000171926
Letter from Airflex Industrial estimating costs to cut holes in metal siding at the 7 World Trade Center penthouse.
Citywide Administrative Services, Dept. of · Box 7DCAS
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · page 6NYC-WTC_000172054
Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Letter regarding OEM Bulletin #1 electrical work, Aug 1998 · page 1NYC-WTC_000172075
Letter detailing scope for graphic annunciator panel and wiring installation.
Citywide Administrative Services, Dept. of · Box 7DCAS
Letter regarding OEM Bulletin #1 sheetmetal work, Aug 24 1998 · page 1NYC-WTC_000172081
Letter detailing costs for sheetmetal mechanical labor and materials.
Citywide Administrative Services, Dept. of · Box 7DCAS
Memo regarding revised change orders #3 and #4, July 1998 · page 1NYC-WTC_000172092
Memorandum summarizing costs for revised change orders submitted for the project.
Citywide Administrative Services, Dept. of · Box 7DCAS
Revised change order #4 submission, Sept 1 1998 · page 2NYC-WTC_000172103
Letter submitting revised change order #4 for $180,087 covering concrete work and graphic annunciator panel installation at 7 WTC.
Citywide Administrative Services, Dept. of · Box 7DCAS
Invoice for closet partition work, Nov 1998 · page 1NYC-WTC_000172204
Invoice from Precision Interiors for framing and trim work on a new closet at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Hardware quotation for OEM Room 23-09, Nov 1998 · page 1NYC-WTC_000172205
Quotation from Bolliers & Contract Hardware to supply finish hardware for room 23-09 at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Change order #4 for cabinetry, Nov 1998 · page 1NYC-WTC_000172208
Proposal from Superior Casework for cabinets and countertops in Room 23-09 at 7 World Trade Center.
Citywide Administrative Services, Dept. of · Box 7DCAS
Ambassador Construction fax cover · page 1NYC-WTC_000172254
Fax cover sheet referencing Ambassador Construction, report #1.
Citywide Administrative Services, Dept. of · Box 7DCAS
Fax regarding TV monitor buttons at EOC, Nov 9 1998 · page 1NYC-WTC_000172263
Fax transmission regarding location of buttons for TV monitors and microwave dish mounting details.
Citywide Administrative Services, Dept. of · Box 7DCAS
Shop drawings transmittal, NOVAUNK, Dec 1998 · page 1NYC-WTC_000172269
Fax transmittal of shop drawings for the Mayor's Office of Emergency Management project dated December 2, 1998.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction proposal for OEM cabinets, May 1998 · page 1NYC-WTC_000172278
Proposal from Superior Casework Inc. dated May 27, 1998, for the construction and installation of cabinets at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Box 7DCAS
Construction cost estimate for OEM World Trade Center project · page 1NYC-WTC_000172283
Bureau of Space Design document estimating construction costs for the Mayor's Office of Emergency Management program at the World Trade Center.