AIA DOCUMENT G701 CONTRACTOR X
FIELD
OTHER
PROJECT: 890094-0300 CHANGE ORDER NUMBER: 32
Mayors Office of Emergency Management
TO (Contractor) ARCHITECTS PROJECT NO.
Ambassador Construction Company CONTRACT FOR: 7 World Trade Center
317 Madison Avenue
New York, NY 10017
CONTRACT DATE: 7/10/98
You are directed to make the following changes in this Contract:
Ambassador Change Order #115.................................................. $39,264.00
Furnish and install connected reserve Inergen supply as follows:
Five (5) Inergen cyclinders and cylinder rack to match existing; re-pipe headers in cylinder rack to
match existing.
Two (2) PA" 3000 lb. rated check valves.
One (1) addistional solenoid valve and main reserve switch.
TOTAL COST FOR ABOVE SCOPE: $39,264.00______________
The original Contract Sum was................................................................. .$11,533,019.00
Net change by previous Change Orders.................................................... .$ 1,271,954.00
The Contract Sum prior to this Change Order was.................................. $ 12,818,918.00
The Contract Sum will be (increase) by this Change Order..................... $ 39,264.00
The new Contract Sum including this Change Order will be.................. . $12,858,182.00
The Contract Time will be (unchanged) by ( )days
The Date of Completion as of the date of this Change Order therefore is
Silverstein Properties, Inc, as Managing
Ambassador Construction Agents for 7 World Trade Company
Architect Contractor Owner
260 49* Street
Brooklyn. NY 11220 5 Avenue. NY. NY 10175
Address Address Address
BY BY BY
Date Date BY
NYC-WTC_000171489
OCR can misread numbers and units. Confirm readings against the page image before using them.