NYC 9/11 Public Portal Document
I-
/AMBASSADOR CONSTRUCTION CO, INC.
❖
©
November 16, 1998
Mr. Walter Weems I* A
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #028
Amb. Job # 857-6175
Dear Mr. Weems:
We are pleased to submit herewith our change order #028 for the following work at the above
referenced premises in the amount of ONE THOUSAND FOUR HUNDRED SEVENTY EIGHT
DOLLARS <$1,478.00>;
As per RFI #36, in order to independently feed
ELP-23N and ELP-23N-1, the work which was
already completely will have to be modified and
alter the conduits to make a splice prior to entering
panel ELP-23N and install new wire. Electrical Cost $1,275.00
General Conditions 102.00
Overhead and Fee 83.00
Insurance 18.00
Total $1,478.00
Please notify us if we are to proceed with this work.
If you have any questions, please do not hesitate to contact us.
Very truly yours,
AMBASSADOR CONSTRUCTION CO., INC.
Martin Schneider
Vice President
MS:am
cc: Juan Mejia - SHO
Glenn Pymento - DCAS
Accepted__________ Dated
C \WPWlN60\WPOOCS\OEM\OEMCO28 WPD
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762