Change order for electrical riser installation, 7 World Trade Center,

Machine-extracted title · confidence 95%

Proposal to install galvanized conduit and fiber optic cables between the loading dock and 23rd floor LAN room for $45,000.

NYC-WTC_000171626–000171628

Folder label: “MOEM - 7 WTC®Fiber Optic Riser”

Page image
Scanned page image, NYC-WTC_000171626
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

i ’JL 7-“ T’. 349 9762 TO 6693640 P.02^0J

I

RoIbERT B. SAMUELS INC.

t

j t j

NovortbqrQ, 1999

Ambassador Construction Company 317 Madison Avenue New York, NY 10017

Attn; Mr. Martin Schneider Re: M0FM-7WrC Fiber Optic Riser

Dear Bit

As par your request, we will provide the following electrical work for the sum of S4S,c 00.00.

1. ! 2-1/2“ Galvanized conduit from the loading dock to the frame room. 2. 2-1/2’ Galvanized riser from frame room to 23"* floor, just outside of the “A" telephone closet. 3. (2) 24 Strand fiber optic cables from the loading dock to the frame room and from the frame room to the 23"* floor LAN room. We will access the existing cable tray from the"A° closet to the LAN room. 4. (1) 120 volt 15 Amp outlet in the 2”* floor frame room. The will be fed from a small transformer tn the pump room off the loading dock.

If it is required to complete th© work by December 1, 1999, please add $5,0jt0.00 for premium labor. We Exclude the following: 1. Overtime. 2. Fiber optic terminations and testing. 3. Patching & painting.

Plee se note the plenum type cable has a 4 week lead time.

3S2 PARK AVENUE SOUTH/ NEW YORK 10010 / S86-6700 / FAX: 2X3-4009

NYC-WTC_000171626

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171626Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #15 sleeves, 7 WTC, Oct 1998 · Box 7DCAS

NYC-WTC_000168650

Change Order #15 submitted by Ambassador Construction for sleeve installation at the 23rd floor of 7 World Trade Center dated October 8, 1998.

1 shared topics · Same agency, volume and box · similarity 0.941

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000168623 · Box 7DCAS

Ambassador Construction submits Change Order #022 for installing multi-mode fiber optic cables at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171910 · Box 7DCAS

Ambassador Construction submits Change Order #022 for fiber optic installation at the Mayor's Office of Emergency Management on October 30, 1998.