AMBASSADOR CONSTRUCTION CO., INC.
I
November 19,1999
Mr. Waiter Weems
Silverstein Properties, Inc.
7 W( rid Trade Center
New York, N.Y. 10048
Re; Mayor's Office Of Emergency Management
7 World Trade Center
Change Order# 106
Dear Mr. Weems:
We gre pleased to submit herewith our change order #105 to perform the following work
at the; above referenced premises for the sum of ONE HUNDRED THIRTY SIX
THOUSAND ONE DOLLAR ($136,001.00).
In accordance with Shem Milson & Wilkes. Inc., audiovisual specification for the system
expa ision; Phase 1 and the drawings AV-1 &AV-2 dated 11/15/99 for the library and
head end expansion.
BREAKDOWN OF COSTS
AceJ Judio $113,044.00
EfeCt ical Work $1,500.00
Eatct & Painting SZbflO.OO
Subtotal $117,044.00
General Condition $9,363.00
Overhead & Fee $7,584.00
Insurance $2,010.00
Note All work on regular working hours Total $136,001.00
Continued....
317 MADISON WENUE . NEW YORK. NY 10017 * 212 922 1020 • FAX 212 949 9762
NYC-WTC_000171607