Change Order #26 submission, 7 WTC, Nov 1998 · Box 7DCASNYC-WTC_000171821
Letter from Ambassador Construction submitting change order #26 for drywall and electrical patching work at the Mayor's Office of Emergency Management.
2 shared non-person entities · Same agency, volume and box · similarity 0.918
Construction cost estimate, 7 World Trade Center Ground & 2nd · Box 7DCASNYC-WTC_000171343
Cost breakdown for enclosing shafts and columns at the ground and second floors of 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.912
Drywall insulation and hardware work estimate, 7 WTC, Jan 2000 · Box 7DCASNYC-WTC_000171511
Construction estimate for partition insulation, drywall work, and hardware installation on 7th floor of 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.908
P&S Industries quote for kitchen appliances, May 1998 · Box 7DCASNYC-WTC_000172309
Quote from P&S Industries listing refrigerators, microwaves, and dishwashers for the Mayor's Office at 7 World Trade Center.
Same agency, volume and box · similarity 0.902
Construction cost estimate, 7 WTC OEM, Feb 1998 · Box 7DCASNYC-WTC_000170825
Ambassador Construction submits a $10.8 million cost estimate for demolition and fit-out work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.901
Subcontractor bid list fax, Ambassador Construction, May 22 1998 · Box 7DCASNYC-WTC_000167929
Fax cover sheet from Ambassador Construction Co. dated May 22, 1998, listing subcontractor bidders for the Mayor's Office of Emergency Management at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.898
Change Order #38 submission for construction work, Dec 1998 · Box 7DCASNYC-WTC_000171840
Letter submitting Change Order #38 for $8,346.00 for unspecified scope of work at the Office of Emergency Management.
Same agency, volume and box · similarity 0.897
Construction bid proposal, 7 World Trade Center, Feb 1998 · Box 7DCASNYC-WTC_000170836
Submission of a ten million dollar construction bid for demolition and tenant fit-out on the 7th and 23rd floors.
Same agency, volume and box · similarity 0.896
Change Order #048 for access door installation, Jan 1999 · Box 7DCASNYC-WTC_000171862
Submission of change order #048 to furnish and install a new 24x24 access door and hardware at room 23-51.
Same agency, volume and box · similarity 0.893
Change order #015 for OEM, 7 World Trade Center, Oct · Box 7DCASNYC-WTC_000171983
Submission of change order #015 by Ambassador Construction Co. to install sleeves and perform firestopping at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.892
RFI log cover sheet, Sep 1998 · Box 7DCASNYC-WTC_000166743
Cover sheet for the Request for Information log documenting 37 received RFI items for the 7 World Trade Center project as of September 16, 1998.
1 shared topics · Same agency, volume and box · similarity 0.892
OEM 7th and 23rd floor preliminary construction budget, February 1998 · Box 7DCASNYC-WTC_000167743
Preliminary construction budget of $10,879,098 for tenant interior fit-out work on the 7th and 23rd floors of 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.891