f-EB 03 ’98 15:02 PR flMBRSSRDOR CONSTR. C0212 949 9762 TO 5517382 P.02/06
AMBASSADOR CONSTRUCTION CQ. INC.
♦
Ms. Cathy Giliberti
February 3,1998
Silverstein Properties, Inc.
120 Broadway
New York, NY 10271
RE: OEM
7 World Trade Center
7th & 23rd Floors
Dear Ms. Giliberti;
We are pleased to submit herewith our Preliminary Budget for the work in accordance with
Swanke Hayden Connell Architects drawings (see attached list) and tenant interior fit-out
project description dated January 26,1998 for the sum of TEN MILLION EIGHT HUNDRED
SEVENTY NINE THOUSAND SIXTY EIGHT DOLLARS ($10,879,068.00).
IHEJEOLLOWltLOJS-O-UK TRADE BREAKDQWftL
Demolition (7th floor) $7,000.00
Drywall 250,000.00
Hollow metal 14.000.00
Hardware 14,000.00
Ceilings 250,000.00
Electric 3,700,000.00
HVAC 1,250.000.00
Plumbing 325,000.00
Painting wallcovering 80,000.00
Floor, Base & Carpet 165.000.00
Iron & Steel 100,000.00
Masonry, Cement 50.000.00
Sprinklers 140,000.00
Architectural Metal 85,000.00
Glass 30,000.00
Ceramic Tile 25.000.00
Woodwork 370,000.00
Projection screen appliance, Toilet accessories, etc. 25,600.00
Raised Floors 91.000.00
Signage (Allowance) 5,000.00
Marble, Stone 34,000.00
Window Treatment 18.500.00
Metal & Glass Partition 75,000.00
Radiator convectors 2,500.00
Movable Partition 14.000.00