AMBASSADOR CONSTRUCTION CO., INC.
i ,/
ly June 10, 1998
Ms. Kathy Giliberti
Silverstein Properties, Inc.
120 Broadway
New York, NY 10271
RE; Mayor’s Office of Emergency Management
7 World Trade Center
1 st, 7th & 23rd Floors
Dear Ms. Giliberti:
We are pleased to submit herewith our revised proposal for the work at the above referenced
area in accordance with Swanke Hayden Connell’s drawings and specifications (see attached
lists) for the sum of ELEVEN MILLION SIX HUNDRED FORTY FIVE THOUSAND SEVEN
HUNDRED FORTY SIX DOLLARS ($11,645,746.00):
Our breakdown is asfollows;
Demolition $13,000.00
Rubbish Removal 0.00 (see Note 1)
Drywall, Carpentry 390,000.00
Hollow Metal 13,120.00
Finish Hardware 30,109.00
Ceilings 289,400.00
*1
Electric & Fixtures 3,784,400.00
*!HVAC 1,433,676.00
Plumbing 389,675.00
Painting/Wallcovering 53,100.00
Floor, Base & Carpet 150,935.00
*lron & steel 187,325.00
*Cement & Concrete 103,325.00
Masonry/Plaster 29,000.00
*Sprinklers 152,400.00
Architectural Metal 178,250.00
Glass, Glazing & Mirrors 22,700.00
Ceramic Tile 29,600.00
Woodwork 256,930.00
Purchase Items 15,509.00 (see Note 2)
Raised Floors 92,300.00
Manhole Cover 1,515.00
Marble, Stone, Terrazzo 5,711.00
Venetian Blinds 19,200.00
Metal & Glass Partition 121,000.00
Fireproofing 7,000.00
Roofing & Waterproofing 49,700.00
Forward.../
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762