AMBASSADOR CONSTRUCTION CO. INC
Mayor’s Office of Emergency Management
7 World Trade Center
June 10. 1998
Page Two...
Breakdown Continued
Furniture 291,143.00 (see Note 3)
*Audio Visual 1,794,194.00
Fabric Wall Panels 19,800.00
Projection Screen 0.00 (see Note 4)
Folding Wall 14,000.00 (see Note 5)
Metal Panel Wall 18,000.00
Special Doors 34,630.00
Metal Shelving 11,726.00
Safe Door 4,130.00
Rolling Fire Door 2,892.00 (see Note 6)
Cut & Patch 30,000.00
Generator Test 4,500.00
Wire Mesh Partition 3,250.00
General Conditions 8% 803,772.00
Overhead & Fee 6% 651,055.00
Insurance 1.25% 14X774.00
Total $11,645,746.00
*Trade values have changed due to Addendum #1 dated 5/15/98 (see attached)
Note 1: Considered a General Conditions cost
Note 2: Reduced by sales tax amount (see P&S proposal attached)
Note 3: Revised quotation received (see Novalink proposal dated 6/1/98 attached)
Note 4; Included in Audio Visual proposals
Note 5: Received new proposal (see The Mackenzie Group proposal dated 6/10/98 attached)
Note 6: Received new proposal (see Metro Door proposal dated 6/9/98 attached)
- Previously approved cost to pre-purchase generator
and switch gear $717,890.00
Qualifications
- Demolition to be performed on week nights
- Use of EMT wiring and rigid conduit for all vertical runs and conduit over 2" diameter
- All furniture devices furnished by vendor
- Furnish and installation of security equipment is based upon Vikonics, Inc.’s drawings and
specifications
- All security wiring to be run in plenum, furnish and installation of conduits is limited to
Drawing TC-101 only
Forward.../
NYC-WTC_000173074