← Document results/7DCAS/7 World Trade Center Mayor's Office of Emergency Management 1st, 7th, & 23rd Floors Chang Order #38
Document / 6 pages

Change Order #38 submission for construction work, Dec 1998

Machine-extracted title · confidence 90%

Letter submitting Change Order #38 for $8,346.00 for unspecified scope of work at the Office of Emergency Management.

NYC-WTC_000171840–000171845

Folder label: “7 World Trade Center Mayor's Office of Emergency Management 1st, 7th, & 23rd Floors Chang Order #38

Page image
Scanned page image, NYC-WTC_000171840
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

y

Silverstein Properties, Inc. I 7 World Trade Center

iBBQBEifetiliilBS New York, N.Y. 10048 Telephone: 212-619-6569 Fax: 212-732-5190

December 9, 1998

Mr. Glenn Pymento Department of City Wide Administrative Services Division of Real Estate Services 1 Centre Street, DRES - Room 2000 North New York, New York 10007 RE: 7 World Trade Center Mayor's Office of Emergency Management-V*, 7*, & 23"^ Floors Chang Order #38______________ Dear Mr. Pymento:

Attached please find change order #38 in the amount of $8,346.00 submitted by Ambassador Construction for the following scope of work.

As per SKP-3 and SKP-4 for additional drains in H.C. toilets 23-32, 23-3 and for installing a new drain in sprinkler closet 23-22 the costs are:

- Plumbing work with overtime for the $5,700.00 floor below - Patching ceiling with overtime $1,500.00

- Subtotal $7,200.00 - General Conditions $576.00 - Overhead and Fee $467.00 - Insurance $103.00 ___ Total $8,34€L0b cjv ^-7,000^ If this meets with your approval, please sign and rerurn to my office. Thank you.

Sincerely,

Walter J. Weems III Building Manager cc: Cathy Giliberti Chi Chu Bill Dacunto Richard Ramos (DCAS) Josep Domingvez (DCAS)

NYC-WTC_000171840

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171840Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change order #91 submission, 7 WTC, July 1999 · Box 7DCAS

NYC-WTC_000168399

Letter from Ambassador Construction submitting change order #91 for $6,565 to remedy leakage on the 7th floor of 7 World Trade Center.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.948

machine-extracted · confidence unavailable · Check page ↗
Change Order #37 submission, Nov 1998 · Box 7DCAS

NYC-WTC_000172213

Letter from Ambassador Construction submitting Change Order #37 for stainless steel cladding at 7 World Trade Center.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.946

machine-extracted · confidence unavailable · Check page ↗
Change Order #26 submission, 7 WTC, Nov 1998 · Box 7DCAS

NYC-WTC_000171821

Letter from Ambassador Construction submitting change order #26 for drywall and electrical patching work at the Mayor's Office of Emergency Management.

4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.945

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000168581 · Box 7DCAS

Ambassador Construction submits Change Order #38 to install additional drains in toilets and a sprinkler closet at 7 World Trade Center.

Similar indexed content

NYC-WTC_000172211 · Box 7DCAS

Submission of change order to waterproof the generator room on the 7th floor using Dex-o-Tex flooring.

Similar indexed content

Compare copies and versions →