NYC 9/11 Public Portal Document
AMBASSADOR CONSTRUCTION CO., INC. E©EDVE
July 22, 1999
s JUL 2 6 1999
fey
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re: Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #091
Amb. Job #557-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #091 to perform the following
work at the above referenced premises for the sum of SIX THOUSAND FIVE
HUNDRED SIXTY FIVE DOLLARS ($6,565.00):
As per Cosentini’s memo to Swanke Hayden Connell regarding the 7th floor
Domestic Booster System bearing drips, the following are the costs associated to
remedy the leakage:
Furnish and install federal pump unit
Furnish and install 2" funnel drain
Connect pump discharge to existing discharge $3,775.00
Furnish and install one (1) separate circuit for pump $1,875.00
Subtotal $5,650.00
General Conditions 452.00
Overhead & Fee 366.00
Insurance 97.00
Total $6,---------
EXCLUSIONS
- Work on overtime
- Vent for pump
Continued...
317 MADISON AVENUE • NEW YORK, NY 10017 • 212 922 1020 • FAX 212 949 9762
NYC-WTC_000171687
OCR can misread numbers and units. Confirm readings against the page image before using them.