11/03Z1998 .17:41 7185969076 ' SUPERIOR CASEWORK PAGE 02
r
UPERIOR
ASEWORK INC.
November 3,1998
Mr. Martin Schneider
Ambassador Construction Co., Inc.
317 Madison Ave.
New York, N.Y. 10017
Dear Martin,
Please accept this change order proposal for the construction delivery, and installation of
cabinets, countertops, and Architectural Woodwork for The Office of Emergency
Management, NYC as per drawing FSK-40 dated 11/2/98. The items included are as
follows:
CHANGE ORDER #2
23-11 12 lin. ft. Corian Countertop -C u
23 sq.ft. Custom Makore v Panelinj; Z ■'
2 lin. ft. Custom Makore Lower
TOTAL including drawings and delivery $ 5,775.00*
♦plus applicable sales tax
TERMS OF PAYMENT:
30% Deposit to Start
30% Upon Delivery
30% After Installation
10% After Completion of Punch L: st
79 BRiDOK St . Brooklyn, NY 11201 . 7lB-B96-09a£ ■ Fax 718-596-9078
NOU 03 1998 16=40 7185969076 PfiGE.02
NYC-WTC_000171819