Miller Druck Specialty Contracting Inc. CHANGE ORDER #_________ 778-01
145 Hudson Street Extra work order as directed by:
New York, New York 10013
Phone: (212)343-3300
Fax; (212)343-3301 I DATE: 1-Dec-98
MDSC JOB #: S-778 VIA TELEFAX
TO: Ambassador Construction
PROJECT: 317 Madison Avenue
7 World Trade Center New York, NY 10017
)Attention: Jack Klein
DESCRIPTION OF WORK
For field labor performed on overtime per attached extra work order:
COST SUMMARY
Description UNIT QTY RATE/PRICE AMOUNT
EWO 50710,10/3/98
Frmn Setter 7 $31.87 S 223.11
Helper 7 $24.45 $ 171.16
Frmn Setter 3 $64.62 S 193.85
Helper 3 $49.37 $ 149.62
Subtotal $ 737.74
Overhead 15% $ 110.66
$ 648.40
Front 10% $ 84.84
PLEASE ISSUE A CHANGE ORDER FOR THE TOTAL
EWO AMOUNT. PAYMENT TERMS SHALL BE PER TOTAL CHANGE ORDER #; 778-01 $ 933.24
SCHEDULE OF SUBCONTRACT.
COMMENTS:
SUBMITTED BY:
MILLER CJ^CK SPECIALTY CONTRACTING INC.
12/16/98 Page 1 778-01r.xls
DEC 16 1998 16=28 PAGE.01
NYC-WTC_000171668