NYC Law Department release
Independent mirror · updated as the City releases more · v1.2.6
← Document results/7DCAS/Change Order # 778-01®7 World Trade Center
Document / 1 page

Change order #778-01 for overtime labor, 7 WTC, Dec 1998

Machine-extracted title · confidence 95%

Change order #778-01 from Miller-Druck for overtime field labor at 7 World Trade Center dated December 1998.

NYC-WTC_000171668

Folder label: “Change Order # 778-01®7 World Trade Center

Page image
Scanned page image, NYC-WTC_000171668
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document :i8-9B MEET 04:24 PF hHX NU, r. U1/U4

Miller Druck Specialty Contracting Inc. CHANGE ORDER #_________ 778-01 145 Hudson Street Extra work order as directed by: New York, New York 10013 Phone: (212)343-3300 Fax; (212)343-3301 I DATE: 1-Dec-98

MDSC JOB #: S-778 VIA TELEFAX TO: Ambassador Construction PROJECT: 317 Madison Avenue 7 World Trade Center New York, NY 10017 )Attention: Jack Klein

DESCRIPTION OF WORK

For field labor performed on overtime per attached extra work order:

COST SUMMARY

Description UNIT QTY RATE/PRICE AMOUNT

EWO 50710,10/3/98 Frmn Setter 7 $31.87 S 223.11 Helper 7 $24.45 $ 171.16 Frmn Setter 3 $64.62 S 193.85 Helper 3 $49.37 $ 149.62

Subtotal $ 737.74 Overhead 15% $ 110.66 $ 648.40 Front 10% $ 84.84

PLEASE ISSUE A CHANGE ORDER FOR THE TOTAL EWO AMOUNT. PAYMENT TERMS SHALL BE PER TOTAL CHANGE ORDER #; 778-01 $ 933.24 SCHEDULE OF SUBCONTRACT. COMMENTS:

SUBMITTED BY: MILLER CJ^CK SPECIALTY CONTRACTING INC.

12/16/98 Page 1 778-01r.xls DEC 16 1998 16=28 PAGE.01

NYC-WTC_000171668

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171668Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171444 · Box 7DCAS

Ambassador Construction letter dated January 29, 1999, submitting Change Order #63 for $1,912 to install a pipe sleeve and cable at 7 World Trade Center.

Similar indexed content

NYC-WTC_000173991 · Box 7DCAS

A transmittal letter submitting Change Order #52 for $38,987 for electrical modifications in a Commissioner's office at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168504 · Box 7DCAS

Memo from Ambassador Construction submitting Change Order #063 for $1,912 to install a pipe sleeve and cabling at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168541 · Box 7DCAS

Memo submitting Change Order #52 for capping outlets and installing new circuits in the Commissioner's office.

Similar indexed content

Compare copies and versions →