FEB 01 ’99 09=09 FR RMBRSSfiDOP C0N5TR. C0212 949 9762 TO 7325190 P.09/13
AMBASSADOR CONSTRUCTION CO, INC
Janua7 29, 1999
Mr Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor's Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floor
Change Order #064
Amb. Job #557-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #064 to perform the following work at the above referenced
premises for the sum of SEVEN THOUSAND ONE HUNDRED FOURTEEN DOLLARS ($7,114.00):
SCOPE OF WORK
1. As per R.B. Samuels' extra work order #28500 (attached), provide manpower
to patch cables in LAN room and TV set server as per Computer Horizons
Labor (9) hours x $95.80 - $862.00
2 As per R.B Samuels' extra work order #28495 (attached), labor for cable
installation and patching of same as requested by Computer Horizons
Labor (24) hours (standard time) x $95.80 = $2,299.00
Labor (16) hours (overtime) x $138.35 = 2,214.00
Material Ze2JQ
Subtotal $6,137.00
General Conditions 491 00
Overhead & Fee 398.00
Insurance aa no
Total $7,114.00
Please issue to us a change order for this work which has been completed.
Vei 'Ours, r
COI INC
Martin schneide/
Vice President
MS:ag
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted:___________ Dated:
e:\wp<)ocstoeniic<»(oernco64.wpd]
317MADISON AVENUE. NEW YORK, NY 10017. 212922 1020, FAX2129499762