Generator load test report for Mayor's Office, August 1999

Machine-extracted title · confidence 93%

Memo detailing a generator load test conducted on August 31, 1999, identifying minor problems with pressure controllers and ATS switches at the Mayor's Office of Emergency…

NYC-WTC_000174096–000174098

Folder label: “Mayor's Office of Emergency Management (Generator Test) Our Job No. 1854

Page image
Scanned page image, NYC-WTC_000174097
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

.03/04 99 03:11 EA.\ 21221902,56 SW.-VNKE H.AYDEN CONNELL 1^00.3/004 08/03/99 16:02 FAX 212 ei-S 3700 ^SEEtlhL,. 121003/004

Mr. Joe Aliotta Swanxe Hayden Connell Page Two CoMfiSni AuociaiM LLP Coruullfng Engineers

3, A simulated power outage was performed on automatic transfer switches (A.T.S.) numbers 2 thru 9, During loss of normal power all “A,T.S’s” transfenred to the alternate ■ power source with no difficulties. Time set points were set on all switches.

4. A simulated pov/er outage was performed on A.T.S. #1. During loss of normal power A.T S.#l started the generators and was on line in approximately 7 seconds. All other switches transfe.Ted to alternate power source.

5. ; A total power outage was performed by opening all transfer switches alternate power discormect switches. Loss of normal power to A.T.S. #1 started the gtmerators. All other transfer switches remained at primary power source position until generators were on line (approximately 7 seconds') and served each of the transfer switch loads.

The following items were noted to be addressed and completed:

1. i Russel Electric to modify their software to perfonu priority load shedding sequence.

‘ Remark: At this point of the system it does not affect the operation to deliver emergency power, but must be incorporated and tested.

2. I Coirect the fuel oil pump system not operating for this test.

Remark; The system is connected to a building fuel pump for temporary use. Operation of system is not affected. I 3. Electrical contractor to label all buss duct and local disconnect switches.

Remark; R.B. Samuels to complete

4. i Correct on all 3 generator's cracks in muffler insulation.

Remark; /ambassador to address.

Combi idg« CSicogo Nbw York Wiuh(ngto»i. DC

NYC-WTC_000174097

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000174097Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Engineering memorandum, job 1854, August 1999 · Box 7DCAS

NYC-WTC_000172539

Engineering consultant memorandum dated August 2, 1999 related to 7 World Trade Center Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.989

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →