SECTION 02082
to allow only certified workers and authorized visitors to enter.
c. Removal of ACSM shall be performed using wet methods. ACSM to be removed
will be thoroughly wetted with amended water or removal encapsulant allowing
adequate time to penetrate the asbestos materials. The adjacent surfaces will also
be wetted prior to removal of ACSM. Dry removal of asbestos-containing
material is prohibited.
d. ACSM will be removed by using hand tools only. The recommended procedure
is to scrape the wetted ACSM directly into the hose nozzle of a HEPA vacuum.
This method will greatly reduce the possibility of fiber release and minimize the
decontamination required within the Work Area.
e. All surfaces from which ACSM was removed shall be free of visible debris or
gross sealant material.
f. Containerize ACSM immediately upon detachment from the substrate.
Alternately, ACSM may be dropped in to a flexible catch basin and promptly
bagged. Excess air within the bag shall be removed before sealing. ACSM shall
not be dropped from a height of greater than 10 feet.
g- A thin coat of an encapsulating agent shall be applied to all surfaces from which
ACSM has been removed.
h. The asbestos handlers shall use personal protective equipment and half-face
filtered respirators during Work Area preparation and during abatement. For Air
monitoring procedures see Part 3 - Testing Laboratory Services.
9 Any modifications to the above procedures (including Air Monitoring) may be made only
upon application to and approval of N.Y.C. Department of Environmental Protection
Asbestos Control Program, Bureau of Air Resources through form ACP-9.
B. Removal of ACM Utilizing Tent Containment Procedures shall be as follows:
1. Preparation Procedures:
a) Ensure that the Testing Laboratory has performed area monitoring and established
a background count prior to the preparatory operations for each removal area, as
applicable.
b) Shut down, isolate, and lock out or tag heating, ventilating, and air conditioning
(HVAC) systems, which pass through the Work Area. Vents within the Work
Area and seams in HVAC components shall be sealed with tape and two layers of
polyethylene sheeting. Filters in HVAC systems shall be removed and treated as
asbestos-contaminated waste.
c) Shut down, disconnect, and lock out or tag all electric power to the Work Area
such as external floodlights, so that there is no possibility of its reactivation until
after clearance testing of the Work Area.
02082-74
CITY_21 MCI 00_014563847