Asbestos Abatement
c) Remove the ACM using hand tools such as knives or
scrapers.
d) Exercise caution when removing ACM.
e) Remove any residual asbestos-containing material from the
substrate using wet cleaning methods.
f) Seal exposed ends of remaining insulation or ACM with a
"wettable cloth" and/or encapsulant.
g) Place the removed material immediately into a properly
labeled 6-mil polyethylene bag. All material shall be properly
containerized and decontaminated prior to removal from the
Work Area.
h) Following the completion of removal of ACM, all visible residue
shall be removed from the substrate.
4. Following Removal of ACM Utilizing Tent Containment or
Tent/Glovebag Procedure:
a) Clean all visible accumulations of loose ACM. Metal shovels
shall not be used within the Work Area.
b) Accumulations of dust shall be cleaned continuously until
completion of clean up.
c) Apply a thin coat of an encapsulating agent shall be applied
to any surfaces in the Work Area which were not the subject
of removal or other remediation activities. In no event shall
encapsulant be applied to any surface that was the subject
of removal or other remediation activities prior to obtaining
satisfactory clearance air monitoring results.
d) After removal of all visible accumulations of ACM, the area
shall be:
(1) HEPA-vacuumed on dry surfaces.
(2) Wet/dry shop vacuums (dedicated to asbestos abatement)
may be used to pick up excess water and gross saturated
debris.
(3) All surfaces shall be wet cleaned. Contractor shall request
and pass a visual inspection performed by the consultant
before proceeding to the next step. Documentation of
CAPITAL PROJECT NUMBER PO79201K 02081-70
100: CONTRACT DOCUMENTS REV. May 3,2000
- 70 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631319
NYC-WTC_000416831
OCR can misread numbers and units. Confirm readings against the page image before using them.