NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 84 pages

Abatement specifications, exterior sealants, P.S. 92M

Machine-extracted title · confidence 45%

CoC/documents for asbestos-containing exterior sealant/caulking materials for DDC school task force, June 2001.

NYC-WTC_000455928–000456011
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082 (2) The area surrounding the abatement work place shall be cleaned of any visible debris utilizing HEPA vacuum and wet methods.

e. The Testing Laboratory will conduct a final visual observation. Approval must be granted prior to break down of decontamination facility and contractor demobilization.

4.02 REMOVAL OF ACSM UTILIZING TENT CONTAINMENT PROCEDURES SHALL BE AS FOLLOWS:

A. Contractor shall be responsible for the proper removal of ACSM from the Work Area using standard industry techniques. The Testing Laboratory representative shall observe the Work.

1. General Requirements

a. Contractor shall install and utilize fixed scaffolding or approved equivalent to facilitate removal of asbestos-containing material from outside the building.

b. All tent enclosures and contiguous spaces within a radius of 10 feet shall be cordoned and regulated to allow only certified workers and authorized visitors to enter.

c. Removal of ACSM shall be performed using wet methods. ACSM to be removed will be thoroughly wetted with amended water or removal encapsulant allowing adequate time to penetrate the asbestos materials. The adjacent surfaces will also be wetted prior to removal of ACSM. Dry removal of asbestos-containing material is prohibited.

d. ACSM will be removed by using hand tools only. The recommended procedure is to scrape the wetted ACSM directly into the hose nozzle of a HEPA vacuum. This method will greatly reduce the possibility of fiber release and minimize the decontamination required within the Work Area.

e. All surfaces from which ACSM was removed shall be free of visible debris or gross sealant material.

f. Containerize ACSM immediately upon detachment from the substrate. Alternately, ACSM may be dropped in to a flexible catch basin and promptly bagged. Excess air within the bag shall be removed before sealing. ACSM shall not be dropped from a height of greater than 10 feet.

g- A thin coat of an encapsulating agent shall be applied to all surfaces from which ACSM has been removed.

h. The asbestos handlers shall use personal protective equipment and half-face filtered respirators during Work Area preparation and during abatement. For Air monitoring procedures see Part 3 - Testing Laboratory Services. 02082-74

CITY_21 MCI 00_014563930

NYC-WTC_000456001

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000456001Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →