SECTION 02082
1) Tent construction shall be performed after pre-cleaning, using the procedures
described in §1-106 of Title 15, Chapter 1. In addition to these requirements, one
extra layer of 6-mil polyethylene sheeting shall also be installed creating a tent
containment that consists of two layers of 6-mil polyethylene sheeting.
o) Pre-Removal Inspections
(1) Prior to removal of any ACM, the Contractor shall notify the Testing
Laboratory and request a pre-removal inspection. Posting of warning
signs, building of decontamination enclosure systems, and all other
preparatory steps have been taken prior to notification of the Testing
Laboratory.
(2) Contractor shall correct any deficiencies observed by Testing Laboratory
at no additional cost to City.
(3) Following the Testing Laboratory’s approval of the Work Area
preparations, removal of ACM may commence.
2. Removal of ACM Within Tent Containment:
a) Abatement shall not be performed in adverse weather conditions (e.g.,
precipitation, heavy winds, etc.)
b) Prior to actual removal, the water sealant shall be blanketed and wetted with a
minimum two-inch thick coating of the acceptable foam or viscous liquid which
shall be maintained for the duration of the removal until the material is bagged.
The foam or viscous liquid shall be confined to the work area.
c) Manual methods of removal are recommended; however, if hand-held power tools
are used to drill, cut into, or otherwise disturb the asbestos-containing roofing
material, the power tools shall be equipped with HEPA-filtered local exhaust
ventilation and operated to prevent potential fiber release.
d) Portable HEPA-vacuum machines shall be available during abatement.
After the ACM removal and bagging, the bagged waste shall be HEPA-vacuumed
then wet cleaned and transferred into the shower room for double bagging. The
double-bagged waste shall be transferred outside the clean room for its final
transfer for storage in an enclosed waste container
3. Following Removal of ACM utilizing Tent Containment Procedures:
a) Remove any visible accumulation of asbestos material and debris. HEPA-
vacuuming and wet cleaning shall be performed on all surfaces inside the Work
Area. All sealed drams, plastic bags, and equipment used in the Work Area shall
be removed from the Work Area.
a) Upon the request of the Contractor, the Testing Laboratory for observing whether
cleaned areas are free of dust, dirt, and debris will do final visual inspection for
02082-76
CITY_21 MCI 00_014563849