Exterior sealant/caulking abatement specs, P.S. 92M

Machine-extracted title · confidence 53%

Specifications for asbestos-containing exterior sealants and caulking materials abatement.

NYC-WTC_000454574–000454656
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082 d) Provide and install remote decontamination enclosure systems in accordance with Articles 3.01 and 3.02 of this Section.

e) Install isolation barriers (i.e., sealing of all openings, including but not limited to windows, corridors, doorways, skylights, ducts, grills, diffusers, and other penetrations within the Work Area) using two layers of 6-mil polyethylene sheeting and duct-tape. Windows within the Work Area and within twenty-five feet of the Work Area shall be sealed with two layers of 6-mil polyethylene sheeting on both interior and exterior surfaces.

f) Construct rigid framework to support Work Area barriers.

(1) Install construction tarpaulin to the outside of the scaffold framing. This tarp shall be installed in lieu of hardwood barriers and shall enclose the outside of the entire scaffolding system.

(2) The construction tarp shall be installed to with stand wind loads accustom to the area and shall remain in place throughout the entire abatement project.

f) Provide a system to collect all water used by the Contractor. Collected water shall be passed through a water filtration system prior to being discharged into the sanitary sewer.

g) Install and initiate operation of AEDs to provide a negative pressure and a minimum or two air changes per hour within the Work Area relative to surrounding non-Work Areas. Do not shut down AEDs until the Work Area is released to the City following final clearance procedures. The use ofHEPA- filtered vacuum to produce a negative air pressure inside the enclosure is prohibited.

h) Maintain emergency and fire exits from the Work Areas or establish alternative exits satisfactory to the local fire officials. Emergency exits and routes shall be established and clearly marked with florescent paint or other effective designations to permit easy location from anywhere within the Work Area. Emergency exits shall be secured to prevent access from uncontaminated areas and yet permit emergency exiting. Exits shall be checked daily against exterior blockage or impediments to exiting.

i) Temporary lighting within the Work Area and decontamination system shall be provided as required to achieve minimum illumination levels.

j) Hand power tools used to drill, cut into, or otherwise disturb ACM shall be equipped with HEPA filtered local exhaust ventilation.

k) Prior to tent construction, the Work Areas shall be cleaned using HEPA vacuum equipment and/or wet cleaning methods as appropriate. Methods that raise dust, such as dry sweeping or vacuuming with equipment not equipped with HEPA filters, shall not be used.

02082-75

CITY_21 MCI 00_014563848

NYC-WTC_000454648

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000454648Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →