Asbestos Abatement
boxes that will the subject of abatement activities. Install
barriers to form a leaktight seal between the Work Area
and adjacent areas. Install isolation barriers in a manner to
endure "negative air pressure" within the Work Area.
(9) Completely seal airtight and isolate the Work Area. All
openings, including but not limited to doorways, tunnels,
ducts, grilles, cracks, diffusers, openings through which
pipe conduit passes, and any other penetrations of the Work
Area, shall be covered with polyethylene sheeting taped or
caulked airtight.
(10) Maintain emergency and fire exits from the Work Areas or
establish alternative exits satisfactory to the local fire
officials. Emergency exits and routes shall be established
and clearly marked with fluorescent paint or other effective
designations to permit easy location from anywhere within
the Work Area. Emergency exits shall be secured to
prevent access from uncontaminated areas and yet permit
emergency exiting. Exits shall be checked daily against
exterior blockage or impediments to exiting.
(11) Temporary lighting within the Work Area and
decontamination system shall be provided as required to
achieve minimum illumination levels.
(12) After isolating the area install and initiate operation of air
filtration devices (AEDs) to provide a negative pressure of
at least -0.02 inches of water and four air changes per hour
within the Work Area relative to surrounding non-Work
Areas. In areas where negative air units can not be
exhausted to the exterior of the station, units shall be
installed in series. When installing units in series, the
exhaust from a AED shall be exhausted into the intake of a
second AED of equal or greater capacity. The exhaust from
the second unit shall be directed to the exterior of the Work
Area in an area that is not accessible to the riding public.
Both units shall be located inside the Work Area. Exhaust
and connect AED using spiral-reinforced tubing
manufactured for this purpose. Do not shut down AEDs
until the Work Area is released to the City following final
clearance procedures.
(13) Hand power tools used to drill, cut into, or otherwise
disturb ACM shall be equipped with HEPA filtered local
CAPITAL PROJECT NUMBER PO79201K 02081-79
100: CONTRACT DOCUMENTS REV. May 3,2000
- 79 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631328
NYC-WTC_000416840
OCR can misread numbers and units. Confirm readings against the page image before using them.