Asbestos abatement technical specifications, 130 Cedar Street, July 2004

Machine-extracted title · confidence 100%

Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.

NYC-WTC_000125579–000125652

Folder label: “130 CEDAR STREET

Page image
Scanned page image, NYC-WTC_000125618
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Asbestos Abatement Technical Specifications For 130 Cedar Street, New York, NY 3.12 Caulk or seal edges of sheeting at floor, ceiling, walls and fixtures to form an airtight seal.

3.13 All entrances to the work place not used for worker entry or emergency exits •

shall be locked and sealed to prevent unauthorized entry.

4.0 Enclosure System and Controls

4.1 The Contractor shall install the DES before any work is performed within the work area.

4.2 The DES shall be built in such a way as to minimize employee exposure when exiting or while passing through adjacent area.

4.3 Constant air monitoring will be conducted in these adjacent areas by the Owner(s) representatives. If fiber levels exceed 0.01 f/cc, all non-licensed workers will be barred from this area, work shall cease, the area shall be cleaned and any problems shall be corrected prior to re-commencement of work.

5.0 Critical Bawler Installation

5.1 The Contractor shall seal all openings from the work area to occupied areas of the building including:

a. Fire Exits must be accessible at all times and each should be •

equipped with an emergency egress air lock to be utilized only in an emergency.

b. Barriers: Critical barriers shall be installed prior to the disturbance of any ACM. Critical barriers (barriers that separate the protected work area from unprotected non-work areas) shall be 18-mil (3 layers of E- mil) fire retardant polyethylene sheeting, individually secured (spray adhesive, then taped), and held in place by wooden frame- work.

a. This framework shall be covered with 3/8-inch minimum sheet-rock material or equivalent, caulked at all joints to provide an airtight seal and shall provide support in both floor ceiling, and work area-non-work area directions.

c. Additional barriers (i.e., sealing off all openings, Including but not limited to windows, corridors, doorways, barriers, skylights, ducts, grills, diffusers, and any other penetrations of the work place) shall be installed with two (2) layers of 6-mil fire retardant polyethylene sealed with tape. All seams of HVAC or other system components that pass through the work place shall also be sealed.

5.2 Should critical barrier erection disturb any ACM, the material shall first be removed by application of amended water and removal using tent procedures

Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 40

NYC-WTC 000125618

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000125618Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000127738 · Box DEP Box 52

Health and safety plan for Phase I deconstruction at 133-135 Greenwich Street and 21-23 Thames Street dated June 8, 2005.

Cited alongside this record in an Ask answer

Compare copies and versions →