NYC 9/11 Public Portal Document
Asbestos Abatement
g) Install and initiate operation of AFDs to provide a negative
pressure and a minimum or two air changes per hour within the
Work Area relative to surrounding non-Work Areas. Do not shut
down AFDs until the Work Area is released to the City following
final clearance procedures. The use of HEPA-filtered vacuums to
produce a negative air pressure inside the enclosure is prohibited.
h) Maintain emergency and fire exits from the Work Areas or
establish alternative exits satisfactory to the local fire officials.
Emergency exits and routes shall be established and clearly
marked with florescent paint or other effective designations to
permit easy location from anywhere within the Work Area.
Emergency exits shall be secured to prevent access from
uncontaminated areas and yet permit emergency exiting. Exits
shall be checked daily against exterior blockage or impediments to
exiting.
i) Temporary lighting within the Work Area and decontamination
system shall be provided as required to achieve minimum
illumination levels.
j) Hand power tools used to drill, cut into, or otherwise disturb ACM
shall be equipped with HEPA filtered local exhaust ventilation.
k) Prior to being plasticized, the Work Areas shall be cleaned using
HEPA-vacuum equipment and/or wet cleaning methods as
appropriate. Methods that raise dust, such as dry sweeping or
vacuuming with equipment not equipped with HEPA filters, shall
not be used.
1) Plasticize the area after pre-cleaning, using the following
procedures. Do not apply polyethylene sheeting wall and ceiling
surfaces that will be demolished to access ACM.
(1) Cover floor with one layer of 6-mil polyethylene sheeting,
turning layer a minimum of 12 inches up wall, and seal
layer to wall.
(2) Cover walls with one layer of 6-mil polyethylene sheeting,
overlapping wall layer a minimum of 12 inches, and seal
layer to floor layer.
(3) Cover ceilings with one layer of 6-mil polyethylene
sheeting, overlapping wall layer a minimum of 12 inches,
and seal layer to wall layer.
CAPITAL PROJECT NUMBER PO79201K 02081-66
100: CONTRACT DOCUMENTS REV. May 3,2000
- 66 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631315
NYC-WTC_000416827