(4) When the encapsulant is dry, second layer of polyethylene sheeting on the
walls, ceiling and floors shall be removed. Do not remove seals from doors,
windows. Isolation Barriers or disconnect the negative pressure equipment.
c) Third Cleaning:
(1) A minimum of four hours after the second cleanup, all the surfaces in the
Work Area shall be HEPA-vacuumed and wet cleaned for a third cleaning.
(2) Upon the request of the Contractor, the Testing Laboratory for observing
whether cleaned areas are free of dust, dirt, and debris will do final visual
inspection for reoccupancy. Evidence of asbestos contamination identified
during the inspection will necessitate further cleaning as heretofore
specified.
(3) When the Work Area passes the Testing Laboratory’s visual reoccupancy
inspection, air sampling shall not begin until at least one hour after the
completion of the third cleanup. The testing laboratory shall perform air
monitoring using aggressive testing techniques. The Testing Laboratory
will approve Reoccupancy if the specified fiber count in the Work Area is
achieved according to the testing laboratory.
(4) When the Work Area passes the reoccupancy test, all controls and seals
established shall be removed.
d) Final Barrier Removal
(1) Upon receipt of acceptable clearance testing results, polyethylene sheeting
and Isolation Barriers shall be removed and disposed accordingly as
asbestos-containing material.
(2) The area surrounding the abatement work place shall be cleaned of any
visible debris utilizing HEPA vacuum and wet methods.
e) The Testing Laboratory will conduct a final visual observation. Approval must be
granted prior to break down of decontamination facility and contractor
demobilization.
4.02 REMOVAL OF ACSM UTILIZING TENT CONTAINMENT PROCEDURES SHALL BE AS
FOLLOWS:
A. Contractor shall be responsible for the proper removal of ACSM from the Work Area using
standard industry techniques. The Testing Laboratory representative shall observe the Work.
1. General Requirements
a. Contractor shall install and utilize fixed scaffolding or approved equivalent to
facilitate removal of asbestos-containing material from outside the building.
2. All tent enclosures and contiguous spaces within a radius of 10 feet shall be cordoned and regulated