Asbestos Abatement
Do not remove seals from doors, windows. Isolation
Barriers or disconnect the negative pressure equipment.
c) Third Cleaning:
(1) A minimum of four hours after the second cleanup, all the
surfaces in the Work Area shall be HEPA-vacuumed and
wet cleaned for a third cleaning.
(2) Upon the request of the Contractor, the Testing Laboratory
for observing whether cleaned areas are free of dust, dirt,
and debris will do final visual inspection for reoccupancy.
Evidence of asbestos contamination identified during the
inspection will necessitate further cleaning as heretofore
specified.
(3) When the Work Area passes the Testing Laboratory's
visual reoccupancy inspection, air sampling shall not begin
until at least one hour after the completion of the third
cleanup. The testing laboratory shall perform air
monitoring using aggressive testing techniques. The
Testing Laboratory will approve Reoccupancy if the
specified fiber count in the Work Area is achieved
according to the testing laboratory.
(4) When the Work Area passes the reoccupancy test, all
controls and seals established shall be removed.
d) Final Barrier Removal
(1) Upon receipt of acceptable clearance testing results,
polyethylene sheeting and Isolation Barriers shall be
removed and disposed accordingly as asbestos-containing
material.
(2) The area surrounding the abatement work place shall be
cleaned of any visible debris utilizing HEPA vacuum and
wet methods.
e) The Testing Laboratory will conduct a final visual observation.
Approval must be granted prior to break down of decontamination
facility and contractor demobilization.
D. Removal of Floor Tile and Mastic Utilizing NYC DEP Variance Attachment FV
shall be as follows:
CAPITAL PROJECT NUMBER PO79201K 02081-77
100: CONTRACT DOCUMENTS REV. May 3,2000
- 77 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631326
NYC-WTC_000416838