NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 84 pages

Abatement specifications, exterior sealants, P.S. 92M

Machine-extracted title · confidence 45%

CoC/documents for asbestos-containing exterior sealant/caulking materials for DDC school task force, June 2001.

NYC-WTC_000455928–000456011
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082 f. Containerize ACSM immediately upon detachment from the substrate. Alternately, ACSM may be dropped in to a flexible catch basin and promptly bagged. Excess air within the bag shall be removed before sealing. ACSM shall not be dropped from a height of greater than 10 feet.

g- A thin coat of an encapsulating agent shall be applied to all surfaces from which ACSM has been removed.

h. The asbestos handlers shall use personal protective equipment and half-face filtered respirators during Work Area preparation and during abatement. For Air monitoring procedures see Part 3 - Testing Laboratory Services.

2. Any modifications to the above procedures (including Air Monitoring) may be made only upon application to and approval of N.Y.C. Department of Environmental Protection Asbestos Control Program, Bureau of Air Resources through form ACP-9.

B. Removal of ACM Utilizing Full Containment Procedures shall be as follows:

1. Preparation Procedures:

a. Ensure that the Testing Laboratory has performed area monitoring and established a background count prior to the preparatory operations for each removal area, as applicable.

b. Shut down, isolate, and lock out or tag heating, ventilating, and air conditioning (HVAC) systems, which pass through the Work Area. Vents within the Work Area and seams in HVAC components shall be sealed with tape and two layers of polyethylene sheeting. Filters in HVAC systems shall be removed and treated as asbestos-contaminated waste.

c. Shut down, disconnect, and lock out or tag all electric power to the Work Area such as external floodlights, so that there is no possibility of its reactivation until after clearance testing of the Work Area.

d. Provide and install contiguous decontamination enclosure systems in accordance with Articles 3.01 and 3.02 of this Section.

e. Install isolation barriers (i.e., sealing of all openings, including but not limited to windows, corridors, doorways, skylights, ducts, grills, diffusers, and other penetrations within the Work Area) using two layers of 6-mil polyethylene sheeting and duct-tape. Windows within the Work Area and within twenty-five feet of the Work Area shall be sealed with two layers of 6-mil polyethylene sheeting on both interior and exterior surfaces.

f. Construct rigid framework to support Work Area barriers.

(1) Apply a solid construction material, minimum thickness of 3/8-inch to the Work Area side of the scaffold framing.

(2) Framework shall be constructed using 2-inch by 4-inch wooden or metal 02082-70

CITY_21 MCI 00_014563926

NYC-WTC_000455997

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000455997Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →