NYC-WTC_000168639
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
4 shared non-person entities · Same agency, volume and box · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗Revised Change Order #16 submitted for electrical work at 7 World Trade Center dated October 19, 1998.
NYC-WTC_000168645–000168646Folder label: “7 World Trade Center Mayor's Office of Emergency Management- 1st, 7th, & 23rd Floors Change Order #16”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
6. Additional switching room 2330, included new and relocated wiring.
Electrical Cost $ 640.00
7. Per drawing E4-02 dated 9/25/98: A. Add one (1) 200 amp, 3 pole and one (1) 70 amp 3 pole breaker in EDPL- 23E. B. Delete one (1) 3 pole 100 amp breaker in EDPL-23E. C. Revise panel ULP-23W and ULP-R from 3 phase 4 wire to 1 phase three wire. D. Add one (1) 50 amp 2 pole breaker in panel ELP-23C1. E. Delete two (2) 1 Samp 1 pole breakers in panels ELP-23C1.
All panels have been delivered and installed with the branch circuitry and feeders. Panel EDPL23-E will have to be replaced in its entirety. All branch and feeder wiring will be removed and then re-installed. Panel ULP23W and R will also have to be replaced. New panels will be provided and re-installed. New breakers will be installed for panel ELP023C-1. Electrical Cost $17,400.00
Sub-total Electrical $30,165.00 Additional Cut and Patch $ 2,500.00 Subtotal $32,665.00 General Conditions $ 2,613.00 Overhead and Fee $ 2,117.00 Insurance $ 467.00 $37,862.00
If this meets with your approval, please sign and return to my office.
Thank you. Sincerely,
Walter J. \^/eems III Building Manager
cc: Cathy Giliberti Chi Chu Bill Dacunto Richard Ramos (DCAS) Josep Domingvez (DCAS)
NYC-WTC_000168646
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000168639
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
4 shared non-person entities · Same agency, volume and box · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173881
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
4 shared non-person entities · Same agency, volume and box · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171903
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
2 shared non-person entities · Same agency, volume and box · similarity 0.958
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168647
Change Order #16 submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated October 15, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.955
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168642
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171897
Ambassador Construction submits Change Order #016R for electrical work at the Mayor's Office of Emergency Management on November 13, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.938
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173884
Ambassador Construction submits Change Order #016R for $21,519 to relocate a panel and tap a transformer at 7 World Trade Center.
1 shared non-person entities · Same agency, volume and box · similarity 0.936
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168630
Change order to provide 277-volt power for fan power boxes by removing existing wiring at 7 World Trade Center.
4 shared non-person entities · Same agency, volume and box · similarity 0.928
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171900
Quotation for electrical modifications including panel relocation, transformer work, dishwasher connection, and fire alarm.
Same agency, volume and box · similarity 0.927
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173820
Letter submitting Change Order #20 for $12,866 to provide power for fan power boxes at 7 World Trade Center.
4 shared non-person entities · Same agency, volume and box · similarity 0.923
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173869
Change order #28 submitted to modify electrical work for independent feeding of ELP-23N equipment.
4 shared non-person entities · Same agency, volume and box · similarity 0.921
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168471
City correspondence reviewing and negotiating costs for numerous submitted change orders related to facility work.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
Similar indexed content
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
Similar indexed content
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
Similar indexed content
Change Order #16 submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated October 15, 1998.
Similar indexed content
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
Similar indexed content