Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
4 shared non-person entities · Same agency, volume and box · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗Revised Change Order #16 submitted for electrical work at 7 World Trade Center dated October 19, 1998.
NYC-WTC_000168645–000168646Folder label: “7 World Trade Center Mayor's Office of Emergency Management- 1st, 7th, & 23rd Floors Change Order #16”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
6. Additional switching room 2330, included new and relocated wiring.
Electrical Cost $ 640.00
7. Per drawing E4-02 dated 9/25/98: A. Add one (1) 200 amp, 3 pole and one (1) 70 amp 3 pole breaker in EDPL- 23E. B. Delete one (1) 3 pole 100 amp breaker in EDPL-23E. C. Revise panel ULP-23W and ULP-R from 3 phase 4 wire to 1 phase three wire. D. Add one (1) 50 amp 2 pole breaker in panel ELP-23C1. E. Delete two (2) 1 Samp 1 pole breakers in panels ELP-23C1.
All panels have been delivered and installed with the branch circuitry and feeders. Panel EDPL23-E will have to be replaced in its entirety. All branch and feeder wiring will be removed and then re-installed. Panel ULP23W and R will also have to be replaced. New panels will be provided and re-installed. New breakers will be installed for panel ELP023C-1. Electrical Cost $17,400.00
Sub-total Electrical $30,165.00 Additional Cut and Patch $ 2,500.00 Subtotal $32,665.00 General Conditions $ 2,613.00 Overhead and Fee $ 2,117.00 Insurance $ 467.00 $37,862.00
If this meets with your approval, please sign and return to my office.
Thank you. Sincerely,
Walter J. \^/eems III Building Manager
cc: Cathy Giliberti Chi Chu Bill Dacunto Richard Ramos (DCAS) Josep Domingvez (DCAS)
NYC-WTC_000168646
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000168639
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
4 shared non-person entities · Same agency, volume and box · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173881
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
4 shared non-person entities · Same agency, volume and box · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171903
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
2 shared non-person entities · Same agency, volume and box · similarity 0.958
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168647
Change Order #16 submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated October 15, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.955
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168642
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171897
Ambassador Construction submits Change Order #016R for electrical work at the Mayor's Office of Emergency Management on November 13, 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.938
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173884
Ambassador Construction submits Change Order #016R for $21,519 to relocate a panel and tap a transformer at 7 World Trade Center.
1 shared non-person entities · Same agency, volume and box · similarity 0.936
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168630
Change order to provide 277-volt power for fan power boxes by removing existing wiring at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.928
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171900
Quotation for electrical modifications including panel relocation, transformer work, dishwasher connection, and fire alarm.
Same agency, volume and box · similarity 0.927
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173820
Letter submitting Change Order #20 for $12,866 to provide power for fan power boxes at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.923
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173869
Change order #28 submitted to modify electrical work for independent feeding of ELP-23N equipment.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.921
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168471
City correspondence reviewing and negotiating costs for numerous submitted change orders related to facility work.
1 shared non-person entities · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000168639
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173881
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
Similarity score 0.990 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168642
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
Similarity score 0.979 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173884
Ambassador Construction submits Change Order #016R for $21,519 to relocate a panel and tap a transformer at 7 World Trade Center.
Similarity score 0.974 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171897
Ambassador Construction submits Change Order #016R for electrical work at the Mayor's Office of Emergency Management on November 13, 1998.
Similarity score 0.963 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171903
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
Similarity score 0.962 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Revised change order for electrical work at 7 World Trade Center dated November 19, 1998.
Similar indexed content
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
Similar indexed content
Ambassador Construction submits Change Order #018 for electrical work at the Mayor's Office of Emergency Management on October 15, 1998.
Similar indexed content
Change Order #16 submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated October 15, 1998.
Similar indexed content
Revised Change Order #16R submitted by Ambassador Construction for electrical panel relocation at 7 World Trade Center dated November 13, 1998.
Similar indexed content