2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.986
machine-extracted · confidence unavailable · Check page ↗Change Order #88 submission, 7 WTC, June 1999
Machine-extracted title · confidence 95%Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.
NYC-WTC_000168409–000168410Folder label: “Mayor's Office of Emergency Management 7 World Trade Center Change Order #088 Amb. Job #S57-5175”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
Mr. Walter Weems June 10, 1999 Page Two. . .
Demolition $2,500.00 Drywall / Carpentry 1500.00 Hollow Metal / Hardware 850.00 Ceilings 4600.00 Electric 6500.00 HVAC 54000.00 Painting 3500.00 Masonry 6000.00 Scaffold 21845.00 Protection 2000.00 Steel Shop Drwg from original C.O. 800.00 Subtotal $104,096.00 General Conditions 8328.00 Overhead & Fee 6745.00 Insurance 1788,00 Total $120,957.00
The original change order #44 for fuel oil line for EIGHTY FIVE THOUSAND DOLLARS ($85,000.00) will be deleted, and this change order will supercede that change order.
We exclude any 2 hour rated fireproofing around this piping.
Please sign one copy of this letter and return it to our office for our records.
If you have any questions please do not hesitate to contact us.
Very truly yours, / / / CONSTRUjfcTIOM CO., INC.
Martin Schneider Vice President
cc: Glenn Pymento/DCAS Juan Mejia/SHC MS:am Accepted:____________ Dated; C OFF1CE\V^WIN\WPOOCS\OEM\CO SvOEMCOU\M’D
AMBASSADOR CONSTRUCTION CO., INC.
NYC-WTC_000168410
OCR can misread numbers and units. Confirm readings against the page image before using them.
Related records
Browse subjects →Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
Same-box records
NYC-WTC_000172231
Submission of Change Order #85 for $34,401 for additional work related to fuel-oil line routing at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.958
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172338
Memo from Ambassador Construction submitting Change Order #85 for fuel oil piping work at the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.958
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168422
Contractor submits Change Order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.957
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172365
Ambassador Construction submits Change Order #85 for $34,401 to adjust fuel-oil line routing in elevator pits at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.947
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168385
Letter submitting change order #97 for enclosing fuel oil lines with sheetrock assembly at the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.946
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171303
Contractor submission of change order #088 to install new fuel oil piping and relocate ductwork at 7 World Trade Center.
2 shared non-person entities · Same agency, volume and box · similarity 0.945
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168407
Letter submitting change order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at 7 World Trade Center.
2 shared non-person entities · Same agency, volume and box · similarity 0.945
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168566
Ambassador Construction submits Change Order #44 to install fuel oil piping and enclosures at 7 World Trade Center.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.943
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171342
Proposal to enclose fuel oil lines with sheetrock instead of vermiculite at the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171739
Letter submitting change order costs for fuel line work at the Mayor's Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171658
Ambassador Construction submits Change Order #078 to remove and reinstall speakers and fire devices at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗Filed elsewhere
No available related records indexed in this group.
More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Others also read
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Contractor submission of change order #088 to install new fuel oil piping and relocate ductwork at 7 World Trade Center.
Filed in the same folder
Similar indexed content
Submission of Change Order #85 for $34,401 for additional work related to fuel-oil line routing at 7 World Trade Center.
Similar indexed content
Memo from Ambassador Construction submitting Change Order #85 for fuel oil piping work at the Mayor's Office of Emergency Management.
Similar indexed content
Contractor submits Change Order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.
Similar indexed content