Mr. Glenn Pymento
June 17,1999
Page Two ...
Painting $3,500.00
Masonry $6,000.00
Scaffold $21,845.00
Steel Shop Drawing from original C/0 $800.00
Subtotal $104,096.00
General Conditions $8,328.00
Overhead and Fee $6,745.00
Insurance $1.788.00
Total $120,957.00
If required by the Port Authority, the 2-hour rated fireproofing around this piping will
cost $100.00 per linear foot. Please add $15,000.00 to the above cost. 2-hour rating
consists of vermiculite plaster with lath.
The original change order #44 for fuel oil line for $85,000.00 will be deleted, and this
change order will supercede that change order.
If this meets with your approval, please sign and return to my office.
Thank you.
Sincerely,
Walter!. Weems III
Building Manager
cc: Cathy Giliberti
Chi Chu
Bill Dacunto
Richard Ramos (DCAS)
Josep Domingvez (DCAS)