← Document results/7DCAS/7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #88
Document / 2 pages

Change order #88 submission, 7 WTC, June 1999

Machine-extracted title · confidence 95%

Letter submitting change order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at 7 World Trade Center.

NYC-WTC_000168407–000168408

Folder label: “7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #88

Page image
Scanned page image, NYC-WTC_000168407
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Silverstein Properties, Inc. 1 7 World Trade Center New York, N.Y. 10048 Telephone; 212-619-6569 Fax: 212-732-5190

June 17,1999 Mr. Glenn Pymento Department of City Wide Administrative Services Division of Real Estate Services 1 Centre Street, DRES - Room 2000 North New York, New York 10007 RE: 7 World Trade Center Mayor's Office of Emergency Management-1^ 7^, & 23"* Firs Change Order #88__________ Dear Mr. Pymento:

Attached please find change order #88 in the amount of $120,957.00 submitted by Ambassador Construction for the following scope of work:

The eight inch conduit which will carry the 114" supply, return and overflow pipe, will run through the second floor machine room corridor into the building communications room and above the lobby ceiling to the fuel oil tank room.

In order for this work to be done, building ductwork must be removed and re­ routed. Also other electrical piping will have to be relocated. The double door for the communications room will be removed and replaced by a single door.

The ceiling lobby sheetrock ceiling will be removed and replaced after the piping is installed.

The lobby area in front of the handicap elevators will have scaffolding so the different trades can work while we keep the elevators operational.

All work is to be performed on normal working hours, except for the scaffolding work. There is no overtime included in the other costs.

Demolition $2,500.00 Drywall/Carpentry $1,500.00 Hollow Metal/Hardware $850.00 Ceilings $4,600.00 Electric $6,500.00 HVAC $54,000.00

Continued . . .

NYC-WTC_000168407

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168407Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change order #85 submission, 7 WTC, May 1999 · Box 7DCAS

NYC-WTC_000168420

Letter submitting change order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.

4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.945

machine-extracted · confidence unavailable · Check page ↗
Change Order #88 submission, 7 WTC, June 1999 · Box 7DCAS

NYC-WTC_000168409

Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.

2 shared non-person entities · Same agency, volume and box · similarity 0.945

machine-extracted · confidence unavailable · Check page ↗
Change Order #85 cover letter, May 1999 · Box 7DCAS

NYC-WTC_000172336

Cover letter submitting Change Order #85 for $34,401 to install new piping for re-routed fuel oil lines at 7 World Trade Center.

5 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.945

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171739 · Box 7DCAS

Letter submitting change order costs for fuel line work at the Mayor's Office of Emergency Management.

Similar indexed content

NYC-WTC_000171765 · Box 7DCAS

Transmittal letter submitting Change Order #44 for fuel oil work at the Mayor's Office of Emergency Management.

Similar indexed content

NYC-WTC_000168565 · Box 7DCAS

Memo submitting Change Order #44 for installing fuel oil piping at the Mayor's Office of Emergency Management in 7 World Trade Center.

Similar indexed content

Compare copies and versions →