Part IV- Waste Management Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701 — August 10, 2005
1.0 General
1.1 Objective
The objective of the Waste Management Plan (WMP) is to characterize, manage,
containerize, and legally transport and dispose of waste streams that will be
generated as part of the 133-135 Greenwich Street/21-23 Thames Street
Deconstruction Project.
1.2. Background
The Copper Group, Inc. has engaged Airtek Environmental Corp. (Airtek) to
prepare the following project plan in support of the de-construction of the
buildings located at 133-135 Greenwich Street and 21-23 Thames Street, New
York, NY. This plan is in response to a request by the WTC Regulators for a
documented approach to the project.
Though they sustained little physical damage, the buildings at 133-135 Greenwich
Street and 21-23 Thames Street were impacted in places by fallout from the
events of September 11, 2001. It is the Owner's intent to conduct abatement of in-
place asbestos, and to effect a decontamination of the interior of the building so
that conventional demolition activities can be completed.
1.3 Abatement Phase
The Abatement Phase of the project includes the cleaning and removal of all
interior surfaces and non-structural elements within the building under
containment. The cleanup and abatement will be conducted so that the building
can be safely deconstructed to allow for redevelopment of the Site. The abatement
Phase project will occur negative pressure containment and includes the following'
general categories: (a) the general area cleanup of WTC, dust and debris, (b)
removal and disposal of installed porous and certain non-porous building
materials and components, (c) cleaning and salvage of certain installed non-
porous building equipment and components, (d) removal of building materials
containing asbestos which were present in the Building prior to September 11th,
2001 (e) packaging of asbestos and other regulated waste including, but not
limited to light bulbs, lighting ballasts, batteries, mercury-containing thermostats,
etc.) at generation points, movement of containers to the decontamination unit and
movement of decontaminated containers to waste loading by hand.
1.4 Conventional Demolition Phase
The Conventional Demolition Phase of the project includes the structural
deconstruction of the remaining cleaned and encapsulated wood framing, and the
masonry facade.